Chain Trencher

SWMS · SWMS-10045

معاينة نموذج SWMS Chain Trencher
  • 14 خطوات عمل
  • اشتُري 71 مرة
  • النسخة 9
  • Earthmoving & Mobile Plant
  • يُقرأ على أي هاتف

This SWMS covers the hazards and controls for chain trencher operations in excavation projects, so that the steps needed to minimise risk and keep the work safe are taken.

It takes your crew through 14 job steps: checking weather and preparing, working alone, transporting the trencher, arriving on site, work area set-up, the environment, housekeeping, manual tasks, communicating with ground workers, trencher operation, changing attachments, refuelling, completion and emergency response.

It suits excavation and trenching contractors, construction companies, utility and infrastructure services, and site supervisors and safety officers.

معاينة SWMS Chain Trencher

Chain Trencher

SWMSVersion 9
Company doing the work
[Company]
Business contact
—
Phone #
—
Responsible person (for monitoring SWMS and work)
—
Signature
—
Date
—
Contact phone #
—
Principal contractor (PC)
[Principal contractor]
PC address
—
PC phone #
[PC phone]
Date SWMS provided to PC
—
Job site address
[Site address]
Is the work associated with a construction project?
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following ‘High-Risk Construction Work’ (HRCW – identified in the Job Task column):

  • Mobile PlantMobile plant movement
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere
  • Traffic CorridorsWork carried out adjacent to a road, railway or shipping lane, traffic corridor

Planning and preparation

Planning

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training and licences

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Eye Protection
  • Sun Protection
  • Seat Belt

Job steps, hazards and controls

  • Work activity

    Check weather conditions & prepare

    • Hazard

      Extreme weather

      Before controls3 High
      Controls
      • Check weather conditions – do not work in extreme conditions

      • Reschedule works to work in more moderate temperatures.

      After controls2 Moderate
      Responsible
      • Supervisorto maintain awareness of weather conditions
      • Operatorto follow controls
    • Hazard

      Hyperthermia / Hypothermia

      Before controls3 High
      Controls
      • Workers trained to recognise the symptoms of hyperthermia and hypothermia

      • Hot conditions. Ensure:

        • Suitable protective clothing

        • Sun brim on hard hats

        • Safety glasses - UV rated

        • Use 30+ sunscreen on exposed skin

        • Adequate drinking water

        • Access to shade on breaks

        • Adequate breaks.

      • Cold conditions. Ensure:

        • Schedule warm-up breaks

        • Hold breaks inside

        • Dress warmly in layers

        • Stay dry (wet clothing chills the body rapidly)

        • Workers must get out of the cold as soon as they can if starting to feel symptoms

        • Alcohol, cigarettes, caffeine and certain medications increase susceptibility to cold.

      After controls2 Moderate
      Responsible
      • Supervisorto maintain awareness of weather conditions
      • Operatorto follow controls

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

13 خطوات عمل أخرى، من Working alone إلى Emergency response

لكل منها مخاطرها وتقييمات خطورتها وإجراءات التحكم فيها، إضافة إلى توقيع طاقمك.

المعاينة بصيغة

كيف يبدو في المتصفح

احصل على هذا النموذج

سجّل مجانًا، ثم اختر الطريقة التي تناسبك. تُعبّأ بيانات شركتك تلقائيًا.

  • مشمول في الخطط المدفوعة

    استخدم أرصدة النماذج من خطتك. تكلفة هذا النموذج 1.

    قارن الخطط والأسعار
  • اشترِه مرة واحدة

    $89.95 تُدفع مرة واحدة، ويبقى ملكك. يعمل على الخطة المجانية أيضًا.

لا حاجة إلى بطاقة للتسجيل. يحصل أعضاء الوصول المبكر على خصم 30% على أي خطة.

ما يغطيه

14 خطوات عمل

  1. Check weather conditions & prepareCheck the weather and protect workers from heat and cold
  2. Working aloneKeep in contact and have first aid ready when working alone
  3. Transporting the trencherLoad, tie down and unload the trencher securely
  4. Arrival on-site & assess onsite conditionsPosition the vehicle, report in and check the site on arrival
  5. Work area set-upSet up exclusion zones and locate underground services
  6. EnvironmentControl noise, dust, waste, spills and other environmental impacts
  7. House keepingKeep the work area clean and free of trip hazards
  8. Manual tasksLift and handle materials safely
  9. Establish a communication system with ground workersAgree communication and approach rules with ground workers
  10. Trencher operationInspect and operate the trencher safely
  11. Changing attachmentsChange attachments and release hydraulic pressure safely
  12. RefuellingRefuel safely with the right fire extinguisher at hand
  13. On completionPark and secure the trencher and sign out
  14. Emergency responseRespond to emergencies and call 000

المخاطر التي يغطيها

المراجعات

لا توجد مراجعات بعد.

اعرض الكل

كيف تعمل النماذج

جرّبه قبل أن تدفع.

  1. معاينة مجانية

    خطوات العمل والمخاطر والمهمة الأولى في كل نموذج متاحة للقراءة. دون تسجيل.

  2. جرّب المحرّر

    كيّف بيان SWMS تجريبيًا باسم شركتك ومهمتك وموقعك، على الحاسوب أو هاتفك.

  3. سجّل مجانًا

    تنتقل بياناتك وشعارك معك. وهذا النموذج يُفتح معبّأً مسبقًا.

  4. استخدم رصيدًا أو اشترِ مرة واحدة

    تتضمن الخطط المدفوعة أرصدة نماذج كل شهر. أو اشترِ هذا النموذج ليبقى لك.