Cladding Removal-Installation Swing Stage

SWMS · SWMS-10491

Vista previa de la plantilla SWMS Cladding Removal-Installation Swing Stage
  • 13 pasos del trabajo
  • Comprado 36 veces
  • Versión 4
  • Carpentry
  • Se lee en cualquier teléfono

This Cladding Removal-Installation Swing Stage Safe Work Method Statement (SWMS) covers hazards and controls for using suspended scaffold systems to remove and install insulation, sarking and cladding.

It covers 13 job steps, from planning, a falls emergency rescue plan and arrival on site to work area set-up, materials and waste delivery, weather, environment, housekeeping and manual tasks, pre-inspection of the system, removing and replacing cladding using a rope system, completion and emergency response.

It suits scaffold operators, facade installation contractors, public works departments and site supervisors.

Vista previa de SWMS Cladding Removal-Installation Swing Stage

Cladding Removal-Installation Swing Stage

SWMSVersion 4
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW – identified in the Job Task column):

  • Gas MainsPressurised gas distribution mains or piping
  • Hazardous Lineschemical, fuel or refrigerant lines
  • Energised Electricalenergised electrical installations or services
  • FallsInvolves a risk of a person falling from 2m or more
  • Telecom Towersincluding work on telecommunications towers

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • High Visibility
  • Head Protection
  • Hand Protection
  • Protective Clothing
  • Sun Protection
  • Safety Harness

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Planning

    • Hazard

      Incorrect system design; system collapse

      Before controls4 Acute
      Controls
      • All components of the suspended scaffold designed and approved by a competent person. (e.g. engineer)

      • Purpose-built suspended scaffolds must:

        • Be verified by an engineer

        • Be clearly marked with the brand name, model number, and serial number

        • Be clearly marked with its capacity and intended use

        • Clearly display the mass in kg of any movable or removable counterweights.

      • Before operating the scaffold, a written statement that the scaffold is complete and safe for use supplied by the person responsible for erecting or altering the scaffold.

      After controls2 Moderate
      Responsible
      • Supervisorto confirm the correct system
    • Hazard

      Lack of planning - potential injury, property damage &/or environmental incident

      Before controls4 Acute
      Controls
      • Liaise with the building owner and obtain as applicable:

        • Drawings

        • Site survey

        • Plan of services

        • Structural engineer report

        • Existing defects

        • All chemicals, volatile fuels and gases have been deactivated

        • Hazardous Materials Registers (asbestos/lead etc.)

        • Relationship to surrounding properties.

      After controls2 Moderate
      Responsible
      • Supervisorto confirm the correct system
    • Hazard

      Regulatory breach

      Before controls3 High
      Controls
      • All notices, permits and licences are in place before work commencing

      • Ensure that written notice is given to the regulator at least 5 days before demolition work commences.

      After controls2 Moderate
      Responsible
      • Supervisorto confirm the correct system
    • Hazard

      Falling objects

      Before controls4 Acute
      Controls
      • Planning access to the height location:

        • Wherever possible, use mechanical methods to deliver materials to the working at height location, e.g. crane

        • Ensure all crane operators, riggers and doggers are licenced, competent and trained in the activity

        • If delivering material/tools onto a raised platform, liaise with Principal to determine where on the platform, the materials are safe to be dropped to:

          • Be able to bear the load

          • Not cause hazards to other trade.

      After controls2 Moderate
      Responsible
      • Supervisorto confirm the correct system

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

12 pasos más del trabajo, de Implement a Falls Emergency Rescue Plan a Emergency response

Cada uno con sus peligros, niveles de riesgo y controles, además de las firmas de tu equipo.

Ver como

Cómo se ve en un navegador

Consigue esta plantilla

Regístrate gratis y luego elige cómo lo quieres. Los datos de tu empresa se rellenan solos.

  • Incluido en los planes de pago

    Usa créditos de plantilla de tu plan. Esta cuesta 1.

    Comparar planes y precios
  • Cómprala una sola vez

    $89.95 pago único, y es tuya para siempre. También sirve con el plan Gratis.

No necesitas tarjeta para registrarte. Los miembros con acceso anticipado tienen un 30% de descuento en cualquier plan.

Qué cubre

13 pasos del trabajo

  1. PlanningPlan the system design, approvals and access
  2. Implement a Falls Emergency Rescue PlanImplement a falls emergency rescue plan
  3. Arrival on-site & assess onsite conditionsCheck the site on arrival
  4. Work area set-upSet up the work area and exclusion zones
  5. Materials & waste delivery & removalDeliver and remove materials and waste
  6. Check weather conditions & prepareCheck the weather and prepare
  7. EnvironmentProtect the environment
  8. House keepingKeep the work area tidy
  9. Manual tasksManage manual tasks safely
  10. Pre-inspect systemInspect the swing stage system before use
  11. Removing & replacing cladding using a rope systemRemove and replace cladding from the rope system
  12. On completionSecure the platform and site on completion
  13. Emergency responseRespond to an emergency

Peligros que cubre

Opiniones

Todavía no hay opiniones.

Ver todo

Cómo funcionan las plantillas

Pruébalo antes de pagar.

  1. Vista previa gratis

    Los pasos del trabajo, los peligros y la primera tarea de cada plantilla se pueden leer. Sin registrarte.

  2. Prueba el editor

    Adapta un SWMS de demostración con tu empresa, tu trabajo y tu obra, en una computadora o en tu teléfono.

  3. Regístrate gratis

    Tus datos y tu logo se pasan. Esta plantilla se abre ya rellenada.

  4. Usa un crédito o compra una sola vez

    Los planes de pago incluyen créditos de plantilla cada mes. O compra esta para quedártela.