Hoist Personnel and Materials

SWMS · SWMS-10618

Vista previa de la plantilla SWMS Hoist Personnel and Materials
  • 7 pasos del trabajo
  • Comprado 115 veces
  • Versión 3
  • Crane & Lifting Equipment
  • Se lee en cualquier teléfono

This Hoist Personnel and Materials Safe Work Method Statement (SWMS) outlines the steps and precautions for safely operating personnel and material hoists, with a focus on reducing the risk of falls from height and other associated hazards.

It covers 7 job steps: training, planning, arrival on site and assessing site conditions, the pre-operational inspection, hoist operation, completion and emergency response.

It suits construction companies, maintenance contractors, safety officers and site supervisors working where hoists are used.

Vista previa de SWMS Hoist Personnel and Materials

Hoist Personnel and Materials

SWMSVersion 3
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • FallsInvolves a risk of a person falling from 2m or more, including work on telecommunications towers

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work.

(specify the hold points)

Training and licences

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • High Visibility
  • Hand Protection
  • Sun Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Training

    • Hazard

      Personal injury

      Before controls3 High
      Controls
      • Ensure all relevant workers have undertaken training and/or received instruction in working at heights (nationally accredited working at heights competency-based training ticket) and all personnel involved in the operation, inspection and maintenance of a hoist are adequately trained and hold a relevant certificate of competency

      • All workers using the suspended hoist must be trained/instructed in the following:

        • The use of the emergency stop, load limiting devices

        • Rescue and emergency evacuation equipment:

          • When the operation of the hoist is to be carried out by a person working alone, make arrangements for communication and rescue in the event of failure

        • Raising and lowering of the hoist, particularly in the event of an emergency, e.g. a power failure

      • How to carry out daily inspections

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

6 pasos más del trabajo, de Planning a Emergency response

Cada uno con sus peligros, niveles de riesgo y controles, además de las firmas de tu equipo.

Ver como

Cómo se ve en un navegador

Consigue esta plantilla

Regístrate gratis y luego elige cómo lo quieres. Los datos de tu empresa se rellenan solos.

  • Incluido en los planes de pago

    Usa créditos de plantilla de tu plan. Esta cuesta 1.

    Comparar planes y precios
  • Cómprala una sola vez

    $89.95 pago único, y es tuya para siempre. También sirve con el plan Gratis.

No necesitas tarjeta para registrarte. Los miembros con acceso anticipado tienen un 30% de descuento en cualquier plan.

Qué cubre

7 pasos del trabajo

  1. TrainingMake sure workers are trained in working at height and hoist operation
  2. PlanningHave a competent person approve and inspect the hoist components
  3. Arrival on-site & assess onsite conditionsAssess the site conditions and safety measures on arrival
  4. Conduct a pre-operational inspectionInspect the hoist components for safety compliance
  5. Hoist operationOperate the hoist safely, including load management and emergency response
  6. On completionSecure the hoist and site on completion
  7. Emergency responseRespond to emergencies involving hoists

Peligros que cubre

Opiniones

Todavía no hay opiniones.

Ver todo

Cómo funcionan las plantillas

Pruébalo antes de pagar.

  1. Vista previa gratis

    Los pasos del trabajo, los peligros y la primera tarea de cada plantilla se pueden leer. Sin registrarte.

  2. Prueba el editor

    Adapta un SWMS de demostración con tu empresa, tu trabajo y tu obra, en una computadora o en tu teléfono.

  3. Regístrate gratis

    Tus datos y tu logo se pasan. Esta plantilla se abre ya rellenada.

  4. Usa un crédito o compra una sola vez

    Los planes de pago incluyen créditos de plantilla cada mes. O compra esta para quedártela.