This Street Sweeper Safe Work Method Statement (SWMS) covers hazards and controls for mechanically powered, regenerative air street sweepers.

It covers 10 job steps: planning, working alone, vehicle operation and street sweeping, obtaining water from a hydrant or another water source, environment, housekeeping, manual tasks, refuelling, completion and emergency response.

It includes controls for high-risk construction work around mobile plant, traffic corridors and hazardous atmospheres, and for minimising environmental impact during street sweeping operations.

It suits local councils and government bodies, commercial cleaning services and environmental service providers.

Vista previa de SWMS Street Sweeper

Street Sweeper

SWMSVersion 6
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following "High-Risk Construction Work" (HRCW - identified in the Job Task column)

  • Mobile PlantMobile plant movement
  • Traffic CorridorsWork carried out adjacent to a road, railway or shipping lane, traffic corridor
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/Review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Seat Belt

Job steps, hazards and controls

  • Work activity

    Planning

    • Hazard

      Unpermitted work

      Before controls3 High
      Controls
      • Obtain written consent from Coordinating Road Authority if applicable. Example:

        • Minor works with no traffic impact = no consent required

        • Where traffic is impacted, consent is required

        • Roads other than freeways, minor works = no consent.

      After controls2 Moderate
      Responsible
      • Supervisors

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

9 pasos más del trabajo, de Working alone a Emergency response

Cada uno con sus peligros, niveles de riesgo y controles, además de las firmas de tu equipo.

Ver como

Cómo se ve en un navegador

Consigue esta plantilla

Regístrate gratis y luego elige cómo lo quieres. Los datos de tu empresa se rellenan solos.

  • Incluido en los planes de pago

    Usa créditos de plantilla de tu plan. Esta cuesta 1.

    Comparar planes y precios
  • Cómprala una sola vez

    $89.95 pago único, y es tuya para siempre. También sirve con el plan Gratis.

No necesitas tarjeta para registrarte. Los miembros con acceso anticipado tienen un 30% de descuento en cualquier plan.

Qué cubre

10 pasos del trabajo

  1. PlanningGet written consent from the Coordinating Road Authority if applicable
  2. Working aloneKeep in contact and check in when working alone
  3. Vehicle operation & street sweepingInspect the sweeper before use and drive and sweep safely
  4. Obtaining water from a hydrant or another water source, e.g. creek/damFill from a hydrant or water source safely, protecting the public
  5. EnvironmentControl noise, pollutants, waste, fuels and spills
  6. HousekeepingKeep the work area clean and clear of slip and trip hazards
  7. Manual tasksManage fatigue, breaks and lumbar support
  8. RefuellingRefuel away from ignition sources and handle fuel safely
  9. On completionPark and secure the truck, inspect it and sign out
  10. Emergency responseCall 000 and follow the site emergency procedures

Peligros que cubre

Opiniones

Todavía no hay opiniones.

Ver todo

Cómo funcionan las plantillas

Pruébalo antes de pagar.

  1. Vista previa gratis

    Los pasos del trabajo, los peligros y la primera tarea de cada plantilla se pueden leer. Sin registrarte.

  2. Prueba el editor

    Adapta un SWMS de demostración con tu empresa, tu trabajo y tu obra, en una computadora o en tu teléfono.

  3. Regístrate gratis

    Tus datos y tu logo se pasan. Esta plantilla se abre ya rellenada.

  4. Usa un crédito o compra una sola vez

    Los planes de pago incluyen créditos de plantilla cada mes. O compra esta para quedártela.