Concrete Sawing and Core Drilling

SWMS · SWMS-10067

  • 작업 단계 13개
  • 버전 12

This Concrete Sawing and Core Drilling Safe Work Method Statement (SWMS) covers the hazards and controls for using a hand-held, electric or petrol/diesel-powered concrete saw and core drill.

It covers 13 job steps, from training, planning and arriving on site to setting up the work area, protecting the environment, checking the weather, housekeeping, manual tasks, cutting and drilling, refuelling, servicing equipment, completion and emergency response.

It includes controls for silica dust, traffic and mobile plant, hazardous atmospheres, fuel, electrical safety and noise.

It suits concrete sawing and drilling companies, construction contractors, site supervisors and project managers.

개별 페이지 보기

Concrete Sawing and Core Drilling SWMS 미리 보기

Concrete Sawing and Core Drilling

SWMSVersion 12
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal contractor (PC)
[Principal contractor]
PC address
—
PC phone
[PC phone]
Date SWMS provided to PC
—
Job site address
[Site address]
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile Plant
  • Pressurised gas distribution mains or piping
  • Chemical, fuel or refrigerant lines
  • Energised electrical installations or services
  • Hazardous Atmosphere

Planning and preparation

Planning

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training and licences

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Head Protection
  • Eye Protection
  • Hand Protection
  • Protective Clothing
  • Breathing Protection
  • Sun Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Training

    • Hazard

      Inhalation of dust

      Before controls3 High
      Controls
      • Training and information provided to workers on respirable crystalline silica (RCS) should include:

        • Identification of RCS dust through Safety Datasheet (SDS) or labels

        • Dust exposure prevention strategies

        • Checking controls are working and using them

        • When and how to use any respiratory protective equipment provided and what to do if something goes wrong (Including worker respirator fit and check processes).

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

작업 단계 12개 더: Planning부터 Emergency response까지

단계마다 위험 요소, 위험도 평가, 관리 조치가 있고, 작업자 서명란도 포함됩니다.

미리 보기 방식

브라우저에서 보이는 모습

이 알뜰 팩 받기

무료로 가입한 뒤 받는 방법을 선택하세요. 모든 문서가 팩 이름으로 된 폴더에 담겨 라이브러리에 들어갑니다.

  • 유료 요금제에 포함

    요금제의 템플릿 크레딧을 사용하세요. 이 팩은 13 대신 10입니다.

    요금제와 가격 비교
  • 한 번 구매하기

    $899.50 $1,169.35 한 번 결제로 계속 소유합니다. 무료 요금제에서도 사용할 수 있습니다.

가입에 카드가 필요 없습니다. 얼리 액세스 회원은 모든 요금제에서 30% 할인을 받습니다.

다루는 내용

작업 단계 13개

  1. TrainingTrain workers about the risk of inhaling dust
  2. PlanningLocate and mark services before cutting or coring
  3. Arrival on-site & assess onsite conditionsCheck the site on arrival and assess its conditions
  4. Work area set-upSet up the work area to protect workers and the public
  5. EnvironmentProtect the surrounding environment during the work
  6. Check weather conditions & prepareCheck the weather and prepare for hot or cold conditions
  7. House keepingKeep the work area clean and clear
  8. Manual tasksReduce the risk of manual handling injuries
  9. Cutting/drillingCut and drill with dust controlled and protective equipment worn
  10. Refuelling equipmentRefuel equipment safely away from ignition sources
  11. Servicing EquipmentService equipment safely
  12. On completionClean up, decontaminate and leave the site safely
  13. Emergency responseFollow the emergency procedures if there is an incident

다루는 위험 요소

템플릿 이용 방법

먼저 써 보고 결제하세요.

  1. 무료 미리 보기

    모든 템플릿의 작업 단계, 위험 요소, 첫 번째 작업 내용을 자유롭게 볼 수 있습니다. 가입이 필요 없습니다.

  2. 에디터 써 보기

    컴퓨터나 휴대폰에서 데모 SWMS에 회사, 작업, 현장 정보를 넣어 보세요.

  3. 무료 가입

    입력한 정보와 로고가 그대로 옮겨집니다. 이 템플릿이 정보가 채워진 상태로 열립니다.

  4. 크레딧 사용 또는 한 번 구매

    유료 요금제에는 매달 템플릿 크레딧이 포함됩니다. 또는 이 템플릿만 구매해 계속 소유하세요.