Plumbing Gas Fitting

SWMS · SWMS-10119

  • कामका 21 चरण
  • संस्करण 7

This SWMS covers the hazards and controls for plumbing gas fitting work: planning to the gas installation standards, excavating and backfilling, bottled gas installation, hot tapping, installing pipework, fitting appliances, purging gas lines, and pressure testing and commissioning.

It takes your crew through 21 job steps, from RCS dust training, confined space checks and weather to housekeeping, manual tasks, tools, hazardous substances, welding and soldering, completion and emergency response. High-risk construction work is marked in the job steps.

It suits plumbing contractors and gas fitters, construction project managers overseeing plumbing and gas fitting work, and the safety officers responsible for it.

Written by SafetyDocs safety experts, who have been writing safety documents since 2004.

यसको आफ्नै पृष्ठ हेर्नुहोस्

Plumbing Gas Fitting SWMS को पूर्वावलोकन

Plumbing Gas Fitting

SWMSVersion 7

Document details

Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal contractor (PC)
[Principal contractor]
PC address
—
PC phone
[PC phone]
Date SWMS provided to PC
—
Job site address
[Site address]
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW – identified in the Job Task column)

  • Mobile PlantMobile plant movement
  • Gas MainsPressurised gas distribution mains or piping chemical, fuel or refrigerant lines energised electrical installations or services
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/Review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • High Visibility
  • Head Protection
  • Face Protection
  • Breathing Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Provide training on the health effects associated with RCS

    • Hazard

      Exposure to respirable crystalline silica (RCS) – dust inhalation

      Before controls3 High
      Controls
      • Training and information provided to workers on RCS should include:

        • Identification of RCS dust through Safety Datasheet (SDS) or labels

        • Dust exposure prevention strategies

        • Checking controls are working and using them

        • When and how to use any respiratory protective equipment provided and what to do if something goes wrong (Including worker respirator fit and check processes).

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

कामका थप 20 चरण, Planning देखि Emergency response सम्म

हरेकमा खतरा, जोखिम रेटिङ र नियन्त्रण, साथै तपाईंको टोलीको साइन-अन।

यसरी पूर्वावलोकन गर्नुहोस्

ब्राउजरमा यो कस्तो देखिन्छ

यो किफायती प्याक लिनुहोस्

निःशुल्क साइन अप गर्नुहोस्, अनि कसरी लिने छान्नुहोस्। हरेक कागजात तपाईंको लाइब्रेरीमा, प्याकको नाम दिइएको फोल्डरमा जान्छ।

  • सशुल्क प्लानहरूमा समावेश

    आफ्नो प्लानका टेम्प्लेट क्रेडिट प्रयोग गर्नुहोस्। यो प्याकको मूल्य 54 को सट्टा 28 हो।

    प्लान र मूल्य तुलना गर्नुहोस्
  • एकपटक किन्नुहोस्

    $2,518.60 $4,857.30 एकपटक तिरेपछि सधैँ तपाईंकै। निःशुल्क प्लानमा पनि चल्छ।

साइन अप गर्न कार्ड चाहिँदैन। प्रारम्भिक पहुँच सदस्यहरूले जुनसुकै प्लानमा 30% छुट पाउँछन्।

यसले के समेट्छ

कामका 21 चरण

  1. Provide training on the health effects associated with RCSTrain workers on RCS dust and its controls
  2. PlanningPlan the gas installation to the standards
  3. Identify Confined Space WorkCheck for confined spaces and get an entry permit
  4. Check weather conditions & prepareCheck the weather and prepare for heat or cold
  5. Arrival on-site & assess onsite conditionsCheck the site, gas supply and site rules on arrival
  6. Work area set-upSet up exclusion zones and check for electrical hazards
  7. EnvironmentControl noise, waste, spills and site impact
  8. House keepingKeep the work area clean and clear
  9. Manual tasksLift and move materials safely
  10. Working with powered & non-powered toolsInspect and use tools safely
  11. Hazardous substance/chemical useHandle chemicals as the SDS directs
  12. Excavating, backfillingLocate services and excavate safely around plant
  13. Bottled Gas installationPlace gas bottles away from ignition sources
  14. Hot TappingPlan hot tapping with an emergency plan
  15. Installing pipeworkInstall pipework safely at height and control dust
  16. Electric or gas welding, soldering & cuttingWeld and cut under a hot work permit
  17. Fitting appliances & fixturesConnect appliances safely to power and gas
  18. Purging gas linesPurge gas lines away from ignition sources
  19. Commission & pressure testPressure test and commission the system
  20. On completionLeave the site safe and certified
  21. Emergency responseRespond to emergencies and give first aid

यसले समेट्ने खतराहरू

टेम्प्लेटहरू कसरी काम गर्छन्

यसलाई पैसा तिर्नुअघि नै चलाएर हेर्नुहोस्।

  1. निःशुल्क पूर्वावलोकन

    हरेक टेम्प्लेटका कामका चरण, खतरा र पहिलो काम पढ्न खुला छन्। साइन अप चाहिँदैन।

  2. एडिटर चलाएर हेर्नुहोस्

    कम्प्युटर वा फोनमा, डेमो SWMS लाई आफ्नो कम्पनी, काम र साइटअनुसार मिलाउनुहोस्।

  3. निःशुल्क साइन अप गर्नुहोस्

    तपाईंको विवरण र लोगो सर्छन्। यो टेम्प्लेट विवरण भरिएरै खुल्छ।

  4. क्रेडिट प्रयोग गर्नुहोस् वा एकपटक किन्नुहोस्

    सशुल्क प्लानहरूमा हरेक महिना टेम्प्लेट क्रेडिट आउँछ। वा सधैँका लागि यो एउटा किन्नुहोस्।