Fuel Storage Tank Installation

SWMS · SWMS-10535

Xem trước mẫu SWMS Fuel Storage Tank Installation
  • 15 bước công việc
  • Phiên bản 3
  • Miscellaneous
  • Đọc được trên mọi điện thoại

This Fuel Storage Tank Installation Safe Work Method Statement (SWMS) outlines the job steps, hazards and safety measures for installing fuel storage tanks. It is a guide to safe and compliant installation practices.

It works through 15 job steps: planning, arrival on site, work area set-up, the environment, housekeeping, checking the weather, manual tasks, materials delivery, mark out and hole excavation, installing the geofabric lining, installing the tank anchors and tank, fittings and pipework, the pressure test, completion and emergency response.

It is suitable for construction companies, fuel storage and handling facilities, environmental management firms and occupational health and safety professionals.

Written by SafetyDocs safety experts, who have been writing safety documents since 2004.

Xem trước SWMS Fuel Storage Tank Installation

Fuel Storage Tank Installation

SWMSVersion 3
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile PlantMobile plant movement
  • Gas MainsPressurised gas distribution mains or piping
  • Hazardous LinesChemical, fuel or refrigerant lines
  • Energised ElectricalEnergised electrical installations or services
  • Shafts & TrenchesWorking at depths greater than 1.5 metres, including tunnels or mines
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere
  • Traffic CorridorsWork carried out adjacent to a road, railway or shipping lane, traffic corridor
  • Water & DrowningIn or near water or other liquid that involves the risk of drowning

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work.

(specify the hold points)

Training/licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • High Visibility
  • Head Protection
  • Hand Protection
  • Protective Clothing
  • Sun Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Planning

    • Hazard

      Injury or death from trench collapse

      Before controls4 Acute
      Controls
      • Implement a site-specific Trench Emergency Response Plan

      • Emergency plan to take into account unexpected incidents, such as ground slip, flooding, gas leaks and the rescue of workers from an excavation.

      After controls2 Moderate
      Responsible
      • Supervisor
    • Hazard

      Unidentified hazards

      Before controls3 High
      Controls
      • All water delivery, excavation and crane work will be outsourced to contractors

      • Liaise with contractors to confirm their SWMS is suitable and available for review

      • All workers are to work under the applicable contractor crane and excavation activity SWMS

      • If a conflict in controls is identified between this SWMS and a contractor SWMS, the work will be stopped until the relevant SWMS are amended, and all workers informed of the changes.

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

Thêm 14 bước công việc, từ Arrival on-site & assess onsite conditions đến Emergency response

Mỗi bước đều có mối nguy, mức rủi ro và biện pháp kiểm soát, cùng phần ký nhận của đội.

Xem trước dạng

Hiển thị thế nào trên trình duyệt

Lấy mẫu này

Đăng ký miễn phí, rồi chọn cách bạn muốn lấy. Thông tin công ty của bạn sẽ được điền sẵn.

  • Có trong các gói trả phí

    Dùng lượt mở mẫu trong gói dịch vụ của bạn. Mẫu này cần 1 lượt.

    So sánh các gói và giá
  • Mua một lần

    $89.95 trả một lần, và mẫu là của bạn mãi mãi. Dùng được cả với gói Miễn phí.

Không cần thẻ để đăng ký. Thành viên truy cập sớm được giảm 30% cho mọi gói.

Nội dung bao gồm

15 bước công việc

  1. PlanningEstablish on-site safety systems and emergency responses
  2. Arrival on-site & assess onsite conditionsEvaluate the site for safety compliance and potential hazards
  3. Work area set-upSecure the area to prevent unauthorised access and ensure safety
  4. EnvironmentMinimise environmental impact and comply with heritage regulations
  5. House keepingMaintain cleanliness to prevent slips, trips and falls
  6. Check weather conditions & preparePrepare for weather conditions to protect against hyperthermia and hypothermia
  7. Manual tasksAddress the risks of manual handling to prevent musculoskeletal injuries
  8. Materials deliveryDeliver and handle materials safely to prevent accidents
  9. Mark out, hole excavation & batteringApply control measures for safe excavation and marking out
  10. Installing geofabric lining (working in the excavation)Apply safety measures for working within excavations
  11. Installing tank anchors, tank, ballasting the tank & backfillingInstall the tank components safely
  12. Installation of fittings, turret, pump, pipework, tank gauging & pump switches to generator skid tankCover electrical safety and component installation
  13. Pressure test to 50psiConduct pressure tests safely
  14. On completionLeave the site secure and safe on completion of work
  15. Emergency responsePrepare for potential emergencies and follow the response actions

Các mối nguy được đề cập

Đánh giá

Chưa có đánh giá nào.

Xem tất cả

Cách các mẫu hoạt động

Dùng thử trước khi trả tiền.

  1. Xem trước miễn phí

    Các bước công việc, mối nguy và nhiệm vụ đầu tiên của mọi mẫu đều mở để đọc. Không cần đăng ký.

  2. Thử trình soạn thảo

    Chỉnh một SWMS demo theo công ty, công việc và công trường của bạn, trên máy tính hoặc điện thoại.

  3. Đăng ký miễn phí

    Thông tin và logo của bạn được chuyển sang. Mẫu này sẽ mở ra với thông tin đã điền sẵn.

  4. Dùng một lượt hoặc mua một lần

    Các gói trả phí có lượt mở mẫu mỗi tháng. Hoặc mua mẫu này để giữ lại.