Plumbing Electrical Safety

SWMS · SWMS-10646

Xem trước mẫu SWMS Plumbing Electrical Safety
  • 14 bước công việc
  • Đã được mua 74 lần
  • Phiên bản 2
  • Plumbing
  • Đọc được trên mọi điện thoại

This SWMS outlines the general electrical hazards of plumbing work, including overhead and underground electrical service hazards and electrical supply faults.

It covers disconnecting hot water services, cutting or disconnecting a metallic water pipe, changing water meters and disconnecting the main earth wire from a water pipe. The work is set out in 14 job steps, from training and arrival on site to commissioning and emergency response.

It suits plumbing professionals, electrical contractors and construction workers doing plumbing work where electrical hazards are present.

Written by SafetyDocs safety experts, who have been writing safety documents since 2004.

Xem trước SWMS Plumbing Electrical Safety

Plumbing Electrical Safety

SWMSVersion 2
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site Management Plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Gas MainsPressurised gas distribution mains or piping
  • Hazardous Lineschemical, fuel or refrigerant lines
  • Energised Electricalenergised electrical installations or services
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere

Planning and preparation

Planning

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training and licences

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment

  • Foot Protection
  • High Visibility
  • Head Protection
  • Face Protection
  • Breathing Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Provide training on electrical hazards associated with plumbing work

    • Hazard

      Electric Shock

      Before controls4 Acute
      Controls
      • Training and information provided to workers on electrical hazards:

        • Workers have a basic understanding of electrical pathways and how water pipes can become ‘live’ in the case of electrical faults

        • Identification of overhead, underground and in-situ electrical hazards

        • Training in controls to manage electrical risk

        • Checking controls are working and using them

        • When and how to use any protective equipment provided and what to do if something goes wrong (emergency response to electric shock).

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

Thêm 13 bước công việc, từ Provide training on the health effects associated with RCS đến Emergency response if co-worker suffers electric shock

Mỗi bước đều có mối nguy, mức rủi ro và biện pháp kiểm soát, cùng phần ký nhận của đội.

Xem trước dạng

Hiển thị thế nào trên trình duyệt

Lấy mẫu này

Đăng ký miễn phí, rồi chọn cách bạn muốn lấy. Thông tin công ty của bạn sẽ được điền sẵn.

  • Có trong các gói trả phí

    Dùng lượt mở mẫu trong gói dịch vụ của bạn. Mẫu này cần 1 lượt.

    So sánh các gói và giá
  • Mua một lần

    $89.95 trả một lần, và mẫu là của bạn mãi mãi. Dùng được cả với gói Miễn phí.

Không cần thẻ để đăng ký. Thành viên truy cập sớm được giảm 30% cho mọi gói.

Nội dung bao gồm

14 bước công việc

  1. Provide training on electrical hazards associated with plumbing workTrain workers on electrical hazards in plumbing work
  2. Provide training on the health effects associated with RCSTrain workers on the health effects of silica dust
  3. Arrival on-site & assess onsite conditionsAssess the site conditions on arrival
  4. Check weather conditions & prepareCheck the weather and prepare for extreme conditions
  5. Work area set-upSet up the work area and establish exclusion zones
  6. Overhead electrical hazardsKeep clear of overhead power lines
  7. Excavation workIdentify and avoid underground services when excavating
  8. Working with power toolsUse power tools safely to prevent electrocution and injury
  9. Cut or disconnect a metallic water pipe.Test for voltage and bridge metallic water pipes before cutting
  10. Welding, solderingPrevent fire and burns during welding and soldering
  11. Fitting appliances & fixturesFit appliances and fixtures safely around electricity
  12. Commission systemPressure test and commission the system
  13. On completionLeave the work area safe and secure
  14. Emergency response if co-worker suffers electric shockRespond to a co-worker who suffers an electric shock

Các mối nguy được đề cập

Đánh giá

Chưa có đánh giá nào.

Xem tất cả

Cách các mẫu hoạt động

Dùng thử trước khi trả tiền.

  1. Xem trước miễn phí

    Các bước công việc, mối nguy và nhiệm vụ đầu tiên của mọi mẫu đều mở để đọc. Không cần đăng ký.

  2. Thử trình soạn thảo

    Chỉnh một SWMS demo theo công ty, công việc và công trường của bạn, trên máy tính hoặc điện thoại.

  3. Đăng ký miễn phí

    Thông tin và logo của bạn được chuyển sang. Mẫu này sẽ mở ra với thông tin đã điền sẵn.

  4. Dùng một lượt hoặc mua một lần

    Các gói trả phí có lượt mở mẫu mỗi tháng. Hoặc mua mẫu này để giữ lại.