Pumpset-Sprinklers-Tanks Inspection Testing

SWMS · SWMS-10666

Xem trước mẫu SWMS Pumpset-Sprinklers-Tanks Inspection Testing
  • 20 bước công việc
  • Phiên bản 3
  • Fire Services
  • Đọc được trên mọi điện thoại

This SWMS covers the general hazards and controls for the inspection and testing of pumpsets, sprinklers and tanks.

It takes your crew through each job step, from planning, client consultation and checking the weather to testing procedures, pressure testing, confined space, electrical hazards, working at height on ladders, refuelling, completion and emergency response.

It suits businesses and contractors who inspect and test pumpsets, sprinklers and tanks, particularly on construction projects where these systems are critical, and the safety officers, site supervisors and workers directly involved.

Written by SafetyDocs safety experts, who have been writing safety documents since 2004.

Xem trước SWMS Pumpset-Sprinklers-Tanks Inspection Testing

Pumpset-Sprinklers-Tanks Inspection Testing

SWMSVersion 3
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site Management Plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following 'High-Risk Construction Work' (HRCW - identified in the Job Task column)

  • FallsInvolves a risk of a person falling from 2m or more, including work on telecommunications towers
  • Gas MainsPressurised gas distribution mains or piping
  • Hazardous LinesChemical, fuel or refrigerant lines
  • Energised ElectricalEnergised electrical installations or services
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/Review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal Protective Equipment (PPE)

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Head Protection
  • Eye Protection
  • Hand Protection
  • Protective Clothing
  • Breathing Protection
  • Safety Harness

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Planning

    • Hazard

      Fire alarm out of commission

      Before controls3 High
      Controls
      • System drawings are available. If records are not readily available, a pre-work survey to identify the system must be conducted

      • The appropriate notice MUST be given to enable isolations to occur if required.

      After controls2 Moderate
      Responsible
      • Supervisor
    • Hazard

      Working alone; Emergency

      Before controls3 High
      Controls
      • Have a reliable communication system in place and test regularly

      • All workers trained in communication protocol:

        • Mobile phones are to be kept on the worker at all times and switched on

        • Lone workers must call the supervisor upon arrival and departure, and regular call-ins made

        • Call-in times must be agreed upon with relevant workers and supervisors and based on the risk level expected at the site

        • Supervisor must have address details, expected arrival/departure & visit duration times

        • Workers only attend the site as directed by the supervisor

        • Emergency procedures are in place if call-ins are not followed or communication is lost with the worker.

      After controls2 Moderate
      Responsible
      • Supervisor
    • Hazard

      Exposure to disease, bites & stings from insects

      Before controls3 High
      Controls
      • Check worksite for vermin/infestation and have removed before commencing work

      • Appropriate application of insect repellent

      • First aid kit readily available

      • Watch out of snakes and spiders

      • Ensure correct and mandatory PPE is worn at all times

      • people with known allergic responses should consult a doctor and ensure an appropriate kit is available at all times (Including EpiPen - in date).

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

Thêm 19 bước công việc, từ Client consultation & code of conduct đến Emergency response

Mỗi bước đều có mối nguy, mức rủi ro và biện pháp kiểm soát, cùng phần ký nhận của đội.

Xem trước dạng

Hiển thị thế nào trên trình duyệt

Lấy mẫu này

Đăng ký miễn phí, rồi chọn cách bạn muốn lấy. Thông tin công ty của bạn sẽ được điền sẵn.

  • Có trong các gói trả phí

    Dùng lượt mở mẫu trong gói dịch vụ của bạn. Mẫu này cần 1 lượt.

    So sánh các gói và giá
  • Mua một lần

    $89.95 trả một lần, và mẫu là của bạn mãi mãi. Dùng được cả với gói Miễn phí.

Không cần thẻ để đăng ký. Thành viên truy cập sớm được giảm 30% cho mọi gói.

Nội dung bao gồm

20 bước công việc

  1. PlanningCheck the system, plan the work and coordinate with the principal contractor
  2. Client consultation & code of conductConsult the client about hazards and protect the client's property
  3. Check weather conditions & prepareCheck the weather and adjust the work schedule to suit
  4. Arrival on-site & assess onsite conditionsAssess the site conditions and take the necessary precautions
  5. Work area set-upSet up an exclusion zone to keep the public out
  6. Testing proceduresTest and inspect to the standards and schedules
  7. Pressure testingHandle equipment under pressure safely
  8. Confined SpaceUse a dedicated Confined Space SWMS where needed
  9. Working in noisy environmentsManage noise and use hearing protection
  10. Working around pinch pointsTake precautions around pinch points and machinery
  11. Working in dust/fumesProtect against dust and fumes
  12. House keepingKeep the work area clean and safe
  13. Manual tasksAvoid musculoskeletal injuries in manual tasks
  14. Electrical hazardsTake precautions near electrical utilities
  15. Working with powered & non-powered toolsUse powered and non-powered tools safely
  16. Working at height on ladders & near openingsUse fall protection on ladders and near openings
  17. Refuelling equipmentHandle fuel safely when refuelling
  18. EnvironmentLimit the impact on the environment
  19. On completionSecure the site after the work
  20. Emergency responseRespond to an emergency

Các mối nguy được đề cập

Đánh giá

Chưa có đánh giá nào.

Xem tất cả

Cách các mẫu hoạt động

Dùng thử trước khi trả tiền.

  1. Xem trước miễn phí

    Các bước công việc, mối nguy và nhiệm vụ đầu tiên của mọi mẫu đều mở để đọc. Không cần đăng ký.

  2. Thử trình soạn thảo

    Chỉnh một SWMS demo theo công ty, công việc và công trường của bạn, trên máy tính hoặc điện thoại.

  3. Đăng ký miễn phí

    Thông tin và logo của bạn được chuyển sang. Mẫu này sẽ mở ra với thông tin đã điền sẵn.

  4. Dùng một lượt hoặc mua một lần

    Các gói trả phí có lượt mở mẫu mỗi tháng. Hoặc mua mẫu này để giữ lại.