Audio Visual Installation

SWMS · SWMS-10014

معاينة نموذج SWMS Audio Visual Installation
  • 17 خطوات عمل
  • اشتُري 141 مرة
  • النسخة 9
  • Shop Fitting
  • يُقرأ على أي هاتف

This Audio Visual Installation Safe Work Method Statement (SWMS) is for the safe installation of audio-visual equipment, covering video conferencing, audio and PA systems, digital signage and home theatre systems. It is a step-by-step guide to managing the hazards and putting control measures in place.

It covers 17 job steps, from silica dust training, planning, arrival on site and locating and isolating existing services to working at height on ladders, trestles and mobile scaffolds, working in roof spaces, running cables, installing and testing equipment, completion and emergency response.

It suits AV installation contractors, construction and renovation companies, event management companies, and corporate IT and facility managers overseeing in-house installations.

معاينة SWMS Audio Visual Installation

Audio Visual Installation

SWMSVersion 9
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW – identified in the Job Task column)

  • Gas MainsPressurised gas distribution mains or piping chemical, fuel or refrigerant lines
  • Energised ElectricalEnergised electrical installations or services
  • FallsInvolves a risk of a person falling from 2m or more, including work on telecommunications towers
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work.

(specify the hold points)

Training and licences

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment

  • Foot Protection
  • High Visibility
  • Head Protection
  • Eye Protection
  • Hand Protection
  • Sun Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Provide training on the health effects associated with RCS

    • Hazard

      Exposure to respirable crystalline silica (RCS) – dust inhalation

      Before controls3 High
      Controls
      • Training and Information provided to workers on RCS should include:

        • Identification of RCS dust through Safety Datasheet (SDS) or labels

        • Dust exposure prevention strategies

        • Checking controls are working and using them

        • When and how to use any respiratory protective equipment provided and what to do if something goes wrong (Including worker respirator fit and check processes).

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

16 خطوات عمل أخرى، من Planning إلى Emergency response

لكل منها مخاطرها وتقييمات خطورتها وإجراءات التحكم فيها، إضافة إلى توقيع طاقمك.

المعاينة بصيغة

كيف يبدو في المتصفح

احصل على هذا النموذج

سجّل مجانًا، ثم اختر الطريقة التي تناسبك. تُعبّأ بيانات شركتك تلقائيًا.

  • مشمول في الخطط المدفوعة

    استخدم أرصدة النماذج من خطتك. تكلفة هذا النموذج 1.

    قارن الخطط والأسعار
  • اشترِه مرة واحدة

    $89.95 تُدفع مرة واحدة، ويبقى ملكك. يعمل على الخطة المجانية أيضًا.

لا حاجة إلى بطاقة للتسجيل. يحصل أعضاء الوصول المبكر على خصم 30% على أي خطة.

ما يغطيه

17 خطوات عمل

  1. Provide training on the health effects associated with RCSProvide training on the health effects associated with RCS
  2. PlanningPlan the electrical load, equipment locations and power sources
  3. Arrival on-site, site assessment & unloading of materials/ equipmentPark safely, report in and set up a safe storage area
  4. Work area set-upBarricade the work area and keep unauthorised people out
  5. Locate & isolate existing servicesLocate, mark and isolate services before drilling
  6. EnvironmentControl noise and sort waste
  7. House keepingKeep the work area clean, lit and clear of trip hazards
  8. Manual tasksLift and move materials safely
  9. Working with powered & non-powered toolsInspect tools and use them as the manufacturer specifies
  10. Working at height on ladders, trestles & mobile scaffoldSet up and use ladders, trestles and mobile scaffolds safely
  11. Working in roof spaceControl electrical, heat, fall, fire and dust hazards in the roof space
  12. New equipment -electrical testingCheck and tag new electrical equipment before use
  13. Running cables/setting up equipmentRun cables and install equipment to specification, clear of hidden services
  14. Lifting, mounting & installing components into positionGround, inspect and secure components as they are mounted
  15. Test & commissionCheck for damage, then restore power and test
  16. On completionClean up, secure the site and sign out
  17. Emergency responseCall 000, follow site emergency procedures and give first aid

المخاطر التي يغطيها

المراجعات

  • It fulfills my SWMS requirements and is relatively easy to tailor.

    Mark Jollyعملية شراء موثّقة

اعرض الكل

كيف تعمل النماذج

جرّبه قبل أن تدفع.

  1. معاينة مجانية

    خطوات العمل والمخاطر والمهمة الأولى في كل نموذج متاحة للقراءة. دون تسجيل.

  2. جرّب المحرّر

    كيّف بيان SWMS تجريبيًا باسم شركتك ومهمتك وموقعك، على الحاسوب أو هاتفك.

  3. سجّل مجانًا

    تنتقل بياناتك وشعارك معك. وهذا النموذج يُفتح معبّأً مسبقًا.

  4. استخدم رصيدًا أو اشترِ مرة واحدة

    تتضمن الخطط المدفوعة أرصدة نماذج كل شهر. أو اشترِ هذا النموذج ليبقى لك.