알뜰 팩 · 템플릿 46개Civil Water and Sewerage Systems Combo에 포함

Pipeline Disinfecting

SWMS · SWMS-10501

  • 작업 단계 12개
  • 버전 3

This Pipeline Disinfecting Safe Work Method Statement (SWMS) covers hazards and controls associated with disinfecting pipelines that will carry potable water.

It covers 12 job steps, from chlorine training, chemical storage and transport, weather checks, arrival on site and work area set-up, through environment, housekeeping and manual tasks, to water quality testing and injecting the mains, fuelling on-site, completion and emergency response.

It suits businesses and contractors involved in pipeline disinfection, particularly those dealing with potable water systems, and the safety officers and site supervisors overseeing high-risk construction work.

개별 페이지 보기

Pipeline Disinfecting SWMS 미리 보기

Pipeline Disinfecting

SWMSVersion 3
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site Management Plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-Risk Construction Work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile PlantMobile plant movement
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere

Planning and Preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold Points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/Review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-Specific Notes

Act, Regulations, Codes of Practice References

None listed.

Personal Protective Equipment (PPE)

  • Foot Protection
  • High Visibility
  • Eye Protection
  • Hand Protection
  • Protective Clothing
  • Breathing Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job Tasks, Hazards and Control Measures

  • Work activity

    Training

    • Hazard

      Exposure to chlorine

      Before controls3 High
      Controls
      • Determine State & Local Authority requirements for notifications, licensing, storage, disposal of hazardous chlorine/substances

        Include:

        • How to read and interpret SDS

        • How to read and interpret labels

        • Specific information about chlorine

        • How to do a chemical risk assessment

        • Correct storage of chlorine

        • Chlorine incompatibilities

        • Disposal methods

        • Spills clean up.

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

작업 단계 11개 더: Chemical storage & transporting부터 Emergency response까지

단계마다 위험 요소, 위험도 평가, 관리 조치가 있고, 작업자 서명란도 포함됩니다.

미리 보기 방식

브라우저에서 보이는 모습

이 알뜰 팩 받기

무료로 가입한 뒤 받는 방법을 선택하세요. 모든 문서가 팩 이름으로 된 폴더에 담겨 라이브러리에 들어갑니다.

  • 유료 요금제에 포함

    요금제의 템플릿 크레딧을 사용하세요. 이 팩은 46 대신 31입니다.

    요금제와 가격 비교
  • 한 번 구매하기

    $2,788.45 $4,137.70 한 번 결제로 계속 소유합니다. 무료 요금제에서도 사용할 수 있습니다.

가입에 카드가 필요 없습니다. 얼리 액세스 회원은 모든 요금제에서 30% 할인을 받습니다.

다루는 내용

작업 단계 12개

  1. TrainingTrain workers in chlorine handling, storage and spill management
  2. Chemical storage & transportingStore and transport chemicals with ventilation and no ignition sources
  3. Check weather conditions & prepareCheck the weather and reschedule if conditions are extreme
  4. Arrival on-site & assess onsite conditionsCheck the site and conditions on arrival and set up safely
  5. Work area set-upSet up an exclusion zone to stop unauthorised access
  6. EnvironmentMinimise environmental impact and manage waste
  7. House keepingKeep the work area clean and clear of trip hazards
  8. Manual tasksAvoid musculoskeletal injuries when lifting and handling
  9. Water quality testing & injecting the mainsTest the water and inject the chlorine mix into the main
  10. Fuelling on-siteRefuel on site and avoid fire and fuel exposure
  11. On completionClean up the site and secure the area
  12. Emergency responseRespond to injuries and environmental damage in an emergency

다루는 위험 요소

템플릿 이용 방법

먼저 써 보고 결제하세요.

  1. 무료 미리 보기

    모든 템플릿의 작업 단계, 위험 요소, 첫 번째 작업 내용을 자유롭게 볼 수 있습니다. 가입이 필요 없습니다.

  2. 에디터 써 보기

    컴퓨터나 휴대폰에서 데모 SWMS에 회사, 작업, 현장 정보를 넣어 보세요.

  3. 무료 가입

    입력한 정보와 로고가 그대로 옮겨집니다. 이 템플릿이 정보가 채워진 상태로 열립니다.

  4. 크레딧 사용 또는 한 번 구매

    유료 요금제에는 매달 템플릿 크레딧이 포함됩니다. 또는 이 템플릿만 구매해 계속 소유하세요.