Fibreglass Pool Installation

SWMS · SWMS-10204

Xem trước mẫu SWMS Fibreglass Pool Installation
  • 17 bước công việc
  • Đã được mua 72 lần
  • Phiên bản 5
  • Swimming Pool
  • Đọc được trên mọi điện thoại

This SWMS covers the steps and safety measures for installing inground fibreglass swimming pools. It identifies the hazards and sets out the controls for a safe and efficient installation.

It takes your crew through each job step, from training, planning and site set-up to excavation, lifting the pool into position, attaching pipework, the pool surround, completion and emergency response. It also covers measures to limit environmental impact.

It suits pool installation companies, construction companies, property management firms, and the site supervisors and safety officers who oversee the work.

Written by SafetyDocs safety experts, who have been writing safety documents since 2004.

Xem trước SWMS Fibreglass Pool Installation

Fibreglass Pool Installation

SWMSVersion 5
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile PlantMobile plant movement
  • Shafts & TrenchesWorking at depths greater than 1.5 metres, including tunnels or mines
  • Gas MainsWork on or near pressurised gas distribution mains or piping
  • Hazardous LinesWork on or near chemical, fuel or refrigerant lines
  • Energised ElectricalWork on or near energised electrical installations or services
  • Traffic CorridorsWork carried out adjacent to a road, railway or shipping lane, traffic corridor

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/Review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • High Visibility
  • Head Protection
  • Hand Protection
  • Protective Clothing
  • Sun Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Training

    • Hazard

      Exposure to respirable crystalline silica (RCS) – dust inhalation

      Before controls3 High
      Controls
      • Training and information provided to workers on RCS should include:

        • Identification of RCS dust through Safety Datasheet (SDS) or labels

        • Dust exposure prevention strategies

        • Checking controls are working and using them

        • When and how to use any respiratory protective equipment provided and what to do if something goes wrong (Including worker respirator fit and check processes).

      After controls2 Moderate
      Responsible
      • Supervisor
    • Hazard

      Powered mobile plant movement

      Before controls4 Acute
      Controls
      • Ensure an effective system of communication between the machine operator and pedestrian workers established before work commences

      • Workers are instructed:

        • Not to approach the machine until the operator has agreed to their request to approach

        • On set distances to maintain from the machine while in operation

        • With the blind spots of the machine.

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

Thêm 16 bước công việc, từ Planning đến Emergency response

Mỗi bước đều có mối nguy, mức rủi ro và biện pháp kiểm soát, cùng phần ký nhận của đội.

Xem trước dạng

Hiển thị thế nào trên trình duyệt

Lấy mẫu này

Đăng ký miễn phí, rồi chọn cách bạn muốn lấy. Thông tin công ty của bạn sẽ được điền sẵn.

  • Có trong các gói trả phí

    Dùng lượt mở mẫu trong gói dịch vụ của bạn. Mẫu này cần 1 lượt.

    So sánh các gói và giá
  • Mua một lần

    $89.95 trả một lần, và mẫu là của bạn mãi mãi. Dùng được cả với gói Miễn phí.

Không cần thẻ để đăng ký. Thành viên truy cập sớm được giảm 30% cho mọi gói.

Nội dung bao gồm

17 bước công việc

  1. TrainingTrain workers in silica dust controls and working around mobile plant
  2. PlanningPlan for trench emergencies, contractors and excavation near structures
  3. Arrival on-site & assess onsite conditionsCheck the site and its conditions on arrival
  4. Work area set-upSet up barricades, exclusion zones and pedestrian access
  5. EnvironmentManage noise, vibration, cultural heritage, water, air quality, waste and fauna
  6. HousekeepingKeep the work area clean to prevent slips, trips and falls
  7. Check weather conditions & prepareWork safely in extreme weather and recognise hyperthermia and hypothermia
  8. Manual tasksPrevent musculoskeletal injuries during manual tasks
  9. Materials deliveryPrevent truck rollover and unload materials safely
  10. ExcavationExcavate safely, locate underground services and manage removed soil
  11. Working in the excavationPrevent ground collapse and work safely inside excavations
  12. Lifting the pool into positionLift and position the pool with licensed operators and rated lifting gear
  13. Attaching pipeworkCut, bend and glue pipework safely
  14. The pool surround - setting formwork and steel reinforcingSet formwork and steel reinforcing, preventing falls and trips
  15. Pool surround - pouring concretePrevent strain injuries when placing concrete
  16. On completionSecure the site and control dust on completion
  17. Emergency responseRespond to injuries, fatalities and environmental damage

Các mối nguy được đề cập

Đánh giá

Chưa có đánh giá nào.

Xem tất cả

Cách các mẫu hoạt động

Dùng thử trước khi trả tiền.

  1. Xem trước miễn phí

    Các bước công việc, mối nguy và nhiệm vụ đầu tiên của mọi mẫu đều mở để đọc. Không cần đăng ký.

  2. Thử trình soạn thảo

    Chỉnh một SWMS demo theo công ty, công việc và công trường của bạn, trên máy tính hoặc điện thoại.

  3. Đăng ký miễn phí

    Thông tin và logo của bạn được chuyển sang. Mẫu này sẽ mở ra với thông tin đã điền sẵn.

  4. Dùng một lượt hoặc mua một lần

    Các gói trả phí có lượt mở mẫu mỗi tháng. Hoặc mua mẫu này để giữ lại.