Gói tiết kiệm · 15 mẫuThuộc Roof Tiling Combo

Roofing Removal

SWMS · SWMS-10640

  • 13 bước công việc
  • Phiên bản 3

This SWMS covers the hazards and controls for removing roofing materials, such as tiles and metal sheeting, from a roof.

It takes your crew through each job step, from the falls emergency rescue plan, arriving on site and setting up the work area to access by mobile scaffold or extension ladder, roof removal, tool and chemical use, completion and emergency response.

It suits roofing contractors, construction companies and demolition crews, and the safety officers and supervisors who run the work, including work involving asbestos, work at height and work near pressurised gas lines.

Written by SafetyDocs safety experts, who have been writing safety documents since 2004.

Xem trang riêng

Xem trước SWMS Roofing Removal

Roofing Removal

SWMSVersion 3
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site Management Plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • AsbestosAsbestos disturbance
  • Gas MainsWork on or near pressurised gas distribution mains or piping
  • Hazardous LinesWork on or near chemical, fuel or refrigerant lines
  • Energised ElectricalWork on or near energised electrical installations or services
  • FallsInvolves a risk of a person falling from 2m or more, including work on telecommunications towers

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/Review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment

  • Foot Protection
  • High Visibility
  • Head Protection
  • Protective Clothing
  • Sun Protection
  • Safety Harness

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Implement a Falls Emergency Rescue Plan

    • Hazard

      Personal injury from fall

      Before controls4 Acute
      Controls
      • Trained first aid providers must be available

      • A reliable means to contact emergency services is available

      After controls2 Moderate
      Responsible
      • Supervisorto ensure the plan is in place

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

Thêm 12 bước công việc, từ Arrival on-site & assess onsite conditions đến Emergency response

Mỗi bước đều có mối nguy, mức rủi ro và biện pháp kiểm soát, cùng phần ký nhận của đội.

Xem trước dạng

Hiển thị thế nào trên trình duyệt

Lấy gói tiết kiệm này

Đăng ký miễn phí, rồi chọn cách bạn muốn lấy. Mọi tài liệu sẽ vào Thư viện của bạn, trong một thư mục mang tên gói.

  • Có trong các gói trả phí

    Dùng lượt mở mẫu trong gói dịch vụ của bạn. Gói này cần 12 lượt thay vì 15 lượt.

    So sánh các gói và giá
  • Mua một lần

    $1,079.40 $1,349.25 trả một lần, và mẫu là của bạn mãi mãi. Dùng được cả với gói Miễn phí.

Không cần thẻ để đăng ký. Thành viên truy cập sớm được giảm 30% cho mọi gói.

Nội dung bao gồm

13 bước công việc

  1. Implement a Falls Emergency Rescue PlanKeep first aid and emergency contact available
  2. Arrival on-site & assess onsite conditionsPosition vehicles safely and complete the site induction
  3. Work area set-upSet up edge protection and fall restraint or arrest systems
  4. Check weather conditions & prepareCheck the weather and plan for heat and cold
  5. EnvironmentManage noise, waste, waterways and fauna
  6. House keepingKeep the work area clean and clear
  7. Manual tasksUse safe lifting techniques
  8. Accessing the roof using mobile scaffolding or extension ladderErect and use the scaffold and ladders safely
  9. Roof removalUse fall restraint or arrest systems and move safely on the roof
  10. Working with powered & non-powered toolsUse powered and non-powered tools safely
  11. Hazardous chemical use, e.g. silicone, cleaning solutionsHandle and use chemicals safely
  12. On completionDismantle the scaffold and clean up the site
  13. Emergency responseRespond to emergencies and follow the rescue plan

Các mối nguy được đề cập

Cách các mẫu hoạt động

Dùng thử trước khi trả tiền.

  1. Xem trước miễn phí

    Các bước công việc, mối nguy và nhiệm vụ đầu tiên của mọi mẫu đều mở để đọc. Không cần đăng ký.

  2. Thử trình soạn thảo

    Chỉnh một SWMS demo theo công ty, công việc và công trường của bạn, trên máy tính hoặc điện thoại.

  3. Đăng ký miễn phí

    Thông tin và logo của bạn được chuyển sang. Mẫu này sẽ mở ra với thông tin đã điền sẵn.

  4. Dùng một lượt hoặc mua một lần

    Các gói trả phí có lượt mở mẫu mỗi tháng. Hoặc mua mẫu này để giữ lại.