Gói tiết kiệm · 9 mẫuThuộc Working at Height

Erecting Fixed Scaffold

SWMS · SWMS-10530

  • 14 bước công việc
  • Phiên bản 7

This Erecting Fixed Scaffold SWMS guides you through the safe erection, dismantling and use of fixed scaffolding.

It takes your crew through 14 job steps, from arriving on site, unloading and checking the weather to erecting the scaffold, working on it, handover, dismantling, completion and emergency response.

It covers height safety, including fall protection and secure access, and planning and assessing site conditions.

It suits construction companies, scaffolding contractors, safety officers and supervisors, and the workers who erect and dismantle scaffolding.

Written by SafetyDocs safety experts, who have been writing safety documents since 2004.

Xem trang riêng

Xem trước SWMS Erecting Fixed Scaffold

Erecting Fixed Scaffold

SWMSVersion 7
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
[Principal contractor]
PC Address
—
PC phone
[PC phone]
Date SWMS provided to PC
—
Job Site Address
[Site address]
Part of a construction project
—

Site Management Plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile Plant
  • Gas Mains
  • Hazardous Lines
  • Energised Electrical
  • FallsInvolves a risk of a person falling from 2m or more, including work on telecommunications towers

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work.

(specify the hold points)

Training and licences

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment

  • Foot Protection
  • High Visibility
  • Head Protection
  • Hand Protection
  • Protective Clothing
  • Sun Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Arrival on-site & assess onsite conditions

    • Hazard

      Personal injury, property damage &/or environmental incident

      Before controls3 High
      Controls
      • The vehicle should be positioned in a safe location, clear of traffic/vehicles/pedestrians during equipment delivery and materials removal (deploy physical barriers, caution signs as necessary)

      • Do not park illegally

      • Identify and obey all safety-related signage (check site entry requirements)

      • Report to Site Supervisor

      • Ensure site-specific induction undertaken

      • Assess mobile phone reception

      • The worksite is exactly as detailed in Terms of Agreement or contract

      • Complete a JSA specifying the control measures for unanticipated hazards.

      After controls2 Moderate
      Responsible
      • Supervisorto check the site and conduct JSA where necessary

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

Thêm 13 bước công việc, từ Unloading scaffolding đến Emergency response

Mỗi bước đều có mối nguy, mức rủi ro và biện pháp kiểm soát, cùng phần ký nhận của đội.

Xem trước dạng

Hiển thị thế nào trên trình duyệt

Lấy gói tiết kiệm này

Đăng ký miễn phí, rồi chọn cách bạn muốn lấy. Mọi tài liệu sẽ vào Thư viện của bạn, trong một thư mục mang tên gói.

  • Có trong các gói trả phí

    Dùng lượt mở mẫu trong gói dịch vụ của bạn. Gói này cần 7 lượt thay vì 9 lượt.

    So sánh các gói và giá
  • Mua một lần

    $629.65 $809.55 trả một lần, và mẫu là của bạn mãi mãi. Dùng được cả với gói Miễn phí.

Không cần thẻ để đăng ký. Thành viên truy cập sớm được giảm 30% cho mọi gói.

Nội dung bao gồm

14 bước công việc

  1. Arrival on-site & assess onsite conditionsSafe setup and preparation before work begins.
  2. Unloading scaffoldingSafe handling and positioning to avoid electrical hazards.
  3. EnvironmentEnvironmental protection measures.
  4. Check weather conditions & preparePrepares workers for weather conditions and environmental factors.
  5. House keepingMaintaining a clean and safe work area.
  6. Manual tasksAims to prevent musculoskeletal injuries through proper handling techniques.
  7. Working with powered & non-powered toolsSafe use of tools to prevent accidents.
  8. Work area set up & pre-inspectionInvolves checking scaffolding components for safety.
  9. Erecting scaffoldProcess for safe assembly.
  10. Working on scaffoldingPrecautions to prevent falls and other injuries.
  11. HandoverScaffolding is safe for use by others.
  12. DismantlingProcess for safely breaking down scaffolding.
  13. On completionSite clean-up and security.
  14. Emergency responsePrepares workers for potential emergencies.

Các mối nguy được đề cập

Cách các mẫu hoạt động

Dùng thử trước khi trả tiền.

  1. Xem trước miễn phí

    Các bước công việc, mối nguy và nhiệm vụ đầu tiên của mọi mẫu đều mở để đọc. Không cần đăng ký.

  2. Thử trình soạn thảo

    Chỉnh một SWMS demo theo công ty, công việc và công trường của bạn, trên máy tính hoặc điện thoại.

  3. Đăng ký miễn phí

    Thông tin và logo của bạn được chuyển sang. Mẫu này sẽ mở ra với thông tin đã điền sẵn.

  4. Dùng một lượt hoặc mua một lần

    Các gói trả phí có lượt mở mẫu mỗi tháng. Hoặc mua mẫu này để giữ lại.