Oferta de acceso anticipado:Acceso anticipado: 30% de descuento, mientras sigas suscrito.

Aprovechar la oferta

Las plantillas están escritas en inglés.

Prueba el editor gratis

Sistema · 114 documentosParte de Glazing Integrated Industry Suite

Glazing Structural

SWMS · SWMS-10487

  • 14 pasos del trabajo
  • Versión 4

This Glazing Structural SWMS outlines the safety control measures for structural glazing. It covers the hazards and controls associated with mobile plant movement, asbestos disturbance, pressurised gas distribution and energised electrical services, and the risk of falls from height.

It sets out 14 job steps, from training on the health effects of respirable crystalline silica, weather checks and site arrival through work area set-up and unloading, tools, hazardous substances, glass handling and movement on site, installing the lifting bracket and connecting the hoist and vacuum lifter, and glass lift and installation, to completion and emergency response.

It includes a risk assessment matrix, controls for each high-risk task and the SWMS sign-off table for workers.

Written by SafetyDocs safety experts, who have been writing safety documents since 2004.

Ver su propia página

Vista previa de SWMS Glazing Structural

Glazing Structural

SWMSVersion 4
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal contractor (PC)
[Principal contractor]
PC address
—
PC phone
[PC phone]
Date SWMS provided to PC
—
Job site address
[Site address]
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW – identified in the Job Task column)

  • Mobile PlantMobile plant movement
  • AsbestosAsbestos disturbance
  • Gas MainsPressurised gas distribution mains or piping
  • Hazardous LinesChemical, fuel or refrigerant lines
  • Energised ElectricalEnergised electrical installations or services
  • FallsInvolves a risk of a person falling from 2m or more, including work on telecommunications towers

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify)

Training and licences

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • High Visibility
  • Head Protection
  • Eye Protection
  • Hand Protection
  • Protective Clothing
  • Breathing Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Provide training on the health effects associated with RCS

    • Hazard

      Exposure to respirable crystalline silica (RCS) – dust inhalation

      Before controls3 High
      Controls
      • Training and information provided to workers on RCS should include:

        • Identification of RCS dust through Safety Datasheet (SDS) or labels

        • Dust exposure prevention strategies

        • Checking controls are working and using them

        • When and how to use any respiratory protective equipment provided and what to do if something goes wrong (Including worker respirator fit and check processes).

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

13 pasos más del trabajo, de Check weather conditions & prepare a Emergency response

Cada uno con sus peligros, niveles de riesgo y controles, además de las firmas de tu equipo.

Ver como

Cómo se ve en un navegador

Consigue este sistema

Regístrate gratis y luego elige cómo lo quieres. Cada documento va a tu Biblioteca, en una carpeta con el nombre del paquete.

  • Incluido en los planes de pago

    Usa créditos de plantilla de tu plan. Esta cuesta 20.

    Comparar planes y precios
  • Cómprala una sola vez

    $999.90 pago único, y es tuya para siempre. También sirve con el plan Gratis.

No necesitas tarjeta para registrarte. Los miembros con acceso anticipado tienen un 30% de descuento en cualquier plan.

Qué cubre

14 pasos del trabajo

  1. Provide training on the health effects associated with RCSTrain workers on the health effects of respirable crystalline silica
  2. Check weather conditions & prepareCheck the weather and prepare for hot or cold conditions
  3. Arrival on-site & assess onsite conditionsCheck the site on arrival and report to the supervisor
  4. Work area set-up & unloadingSet up the work area and unload and store glass safely
  5. EnvironmentLimit the environmental impact of noise, dust, waste, chemicals and vehicles
  6. HousekeepingKeep the work area clean, well lit and free of trip hazards
  7. Manual tasksLift, carry and handle materials and glass safely
  8. Working with powered & non-powered toolsUse powered and non-powered tools safely
  9. Hazardous substance/chemical useUse hazardous chemicals as the SDS directs
  10. Glass handling & movement on-siteMove glass safely around the site
  11. Installing the lifting bracket & connecting the hoist & vacuum lifterFit the lifting bracket and connect the hoist and vacuum lifter from a platform ladder
  12. Glass lift & installationLift and install glass with the hoist and vacuum lifter
  13. On completionClean up, make safe and sign out when the work is finished
  14. Emergency responseRespond to injuries and emergencies

Peligros que cubre

Cómo funcionan las plantillas

Pruébalo antes de pagar.

  1. Vista previa gratis

    Los pasos del trabajo, los peligros y la primera tarea de cada plantilla se pueden leer. Sin registrarte.

  2. Prueba el editor

    Adapta un SWMS de demostración con tu empresa, tu trabajo y tu obra, en una computadora o en tu teléfono.

  3. Regístrate gratis

    Tus datos y tu logo se pasan. Esta plantilla se abre ya rellenada.

  4. Usa un crédito o compra una sola vez

    Los planes de pago incluyen créditos de plantilla cada mes. O compra esta para quedártela.