Cladding Removal-Installation Swing Stage

SWMS · SWMS-10491

Cladding Removal-Installation Swing Stage SWMS模板预览
  • 13 个工作步骤
  • 已售出 36 次
  • 版本 4
  • Carpentry
  • 任何手机都能看

This Cladding Removal-Installation Swing Stage Safe Work Method Statement (SWMS) covers hazards and controls for using suspended scaffold systems to remove and install insulation, sarking and cladding.

It covers 13 job steps, from planning, a falls emergency rescue plan and arrival on site to work area set-up, materials and waste delivery, weather, environment, housekeeping and manual tasks, pre-inspection of the system, removing and replacing cladding using a rope system, completion and emergency response.

It suits scaffold operators, facade installation contractors, public works departments and site supervisors.

Cladding Removal-Installation Swing Stage SWMS 预览

Cladding Removal-Installation Swing Stage

SWMSVersion 4
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW – identified in the Job Task column):

  • Gas MainsPressurised gas distribution mains or piping
  • Hazardous Lineschemical, fuel or refrigerant lines
  • Energised Electricalenergised electrical installations or services
  • FallsInvolves a risk of a person falling from 2m or more
  • Telecom Towersincluding work on telecommunications towers

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • High Visibility
  • Head Protection
  • Hand Protection
  • Protective Clothing
  • Sun Protection
  • Safety Harness

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Planning

    • Hazard

      Incorrect system design; system collapse

      Before controls4 Acute
      Controls
      • All components of the suspended scaffold designed and approved by a competent person. (e.g. engineer)

      • Purpose-built suspended scaffolds must:

        • Be verified by an engineer

        • Be clearly marked with the brand name, model number, and serial number

        • Be clearly marked with its capacity and intended use

        • Clearly display the mass in kg of any movable or removable counterweights.

      • Before operating the scaffold, a written statement that the scaffold is complete and safe for use supplied by the person responsible for erecting or altering the scaffold.

      After controls2 Moderate
      Responsible
      • Supervisorto confirm the correct system
    • Hazard

      Lack of planning - potential injury, property damage &/or environmental incident

      Before controls4 Acute
      Controls
      • Liaise with the building owner and obtain as applicable:

        • Drawings

        • Site survey

        • Plan of services

        • Structural engineer report

        • Existing defects

        • All chemicals, volatile fuels and gases have been deactivated

        • Hazardous Materials Registers (asbestos/lead etc.)

        • Relationship to surrounding properties.

      After controls2 Moderate
      Responsible
      • Supervisorto confirm the correct system
    • Hazard

      Regulatory breach

      Before controls3 High
      Controls
      • All notices, permits and licences are in place before work commencing

      • Ensure that written notice is given to the regulator at least 5 days before demolition work commences.

      After controls2 Moderate
      Responsible
      • Supervisorto confirm the correct system
    • Hazard

      Falling objects

      Before controls4 Acute
      Controls
      • Planning access to the height location:

        • Wherever possible, use mechanical methods to deliver materials to the working at height location, e.g. crane

        • Ensure all crane operators, riggers and doggers are licenced, competent and trained in the activity

        • If delivering material/tools onto a raised platform, liaise with Principal to determine where on the platform, the materials are safe to be dropped to:

          • Be able to bear the load

          • Not cause hazards to other trade.

      After controls2 Moderate
      Responsible
      • Supervisorto confirm the correct system

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

还有 12 个工作步骤,从“Implement a Falls Emergency Rescue Plan”到“Emergency response”

每一步都有危险、风险等级和控制措施,另附工人签到。

预览方式

在浏览器中的样子

获取这个模板

免费注册,然后选择获取方式。你的公司信息会自动填好。

  • 付费套餐包含

    使用套餐中的模板额度。这一份需要 1 个额度。

    比较套餐和价格
  • 单独购买

    $89.95 一次付清,永久归你。免费套餐也能用。

注册无需银行卡。抢先体验会员购买任何套餐都可享 30% 折扣。

涵盖内容

13 个工作步骤

  1. PlanningPlan the system design, approvals and access
  2. Implement a Falls Emergency Rescue PlanImplement a falls emergency rescue plan
  3. Arrival on-site & assess onsite conditionsCheck the site on arrival
  4. Work area set-upSet up the work area and exclusion zones
  5. Materials & waste delivery & removalDeliver and remove materials and waste
  6. Check weather conditions & prepareCheck the weather and prepare
  7. EnvironmentProtect the environment
  8. House keepingKeep the work area tidy
  9. Manual tasksManage manual tasks safely
  10. Pre-inspect systemInspect the swing stage system before use
  11. Removing & replacing cladding using a rope systemRemove and replace cladding from the rope system
  12. On completionSecure the platform and site on completion
  13. Emergency responseRespond to an emergency

涵盖的危险

评价

暂无评价。

查看全部

模板如何使用

在付款前先试用。

  1. 免费预览

    每个模板的工作步骤、危险和第一项任务都可以直接阅读,无需注册。

  2. 试用编辑器

    在电脑或手机上,用你的公司、工作和工地信息修改一份演示 SWMS。

  3. 免费注册

    你的信息和标志都会带过去。这个模板打开时已经填好。

  4. 使用额度或单独购买

    付费套餐每月都包含模板额度。也可以单独购买这一份,永久保留。