Air Compressor
- Company doing the work
- [Company]
- Business contact
- —
- Phone #
- —
- Responsible person (for monitoring SWMS and work)
- —
- Signature
- —
- Date
- —
- Contact phone #
- —
- Principal contractor (PC)
- [Principal contractor]
- PC address
- —
- PC phone #
- [PC phone]
- Date SWMS provided to PC
- —
- Job site address
- [Site address]
- Part of a construction project
- —
Site management plan
If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.
High-risk construction work
This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)
- Mobile Plant
- Hazardous Atmosphere
Planning and preparation
Planning/preparation
Liaise with Principal Contractor to identify on-site safety systems and procedures
Establish supervisory and communication arrangements
Principal contractor to confirm emergency response procedures are in place.
Hold points
Hold points identified and signed off before continuing work. (specify the hold points)
Training and licences
All workers to have a General Construction Induction Card
Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.
Trained First Aider on site
All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.
Worker duties and responsibilities
Fit condition for work, i.e., no signs of fatigue, alcohol or drugs
Attend all site inductions/briefings
Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)
Only carry out work related to the contract
Inspect completed work and report possible safety, environmental and quality matters to the supervisor.
Monitoring and review
All people involved in the task must have this SWMS communicated to them before work commences
SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident
If additional site hazards identified, review this SWMS and amend control measures to suit
People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP
Give the principal contractor a copy of the revised SWMS
The site supervisor to monitor works against the controls stated in this SWMS
SWMS must be kept on-site and made available for inspection or review
Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident
Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.
Site-specific notes
Legislation and codes of practice
None listed.
Personal protective equipment
- Foot Protection
- Hearing Protection
- High Visibility
- Eye Protection
- Hand Protection
- Protective Clothing
- Sun Protection
Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.
Job steps, hazards and controls
- Work activity
Transporting an air compressor
- Hazard
Fire / explosion
Before controls3 HighControlsEnsure the compressor is transported in trailer, or tray of utility – not inside the cabin of the vehicle
Secure fuel containers – outside of the main cabin also
Ensure the fuel valve is in the closed position
Fuel:
Minimum quantities stored
Stored in smaller sized suitable plastic containers (as per relevant Australian Standard)
Containers clearly labelled. Labels in good condition
Fire protection equipment accessible, tested and tagged.
After controls2 ModerateResponsible- Supervisorto ensure control measures followed
- Workersto ensure control measures followed
- Hazard
Struck by moving objects / falling objects
Before controls3 HighControlsEnsure the main vehicle cabin is isolated from the carrier area with a fixed barrier or transport compressor and equipment on a trailer/tray back:
Secure the compressor in the vehicle tray with lashing/restraint equipment to prevent the compressor from moving during transport:
Use chocks to assist keeping the compressor stationary in the tray
Ensure all non-essential people removed from the immediate area
Ensure all people stand clear of potential fall zones during loading /unloading of the compressor.
After controls2 ModerateResponsible- Supervisorto ensure control measures followed
- Workersto ensure control measures followed
IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute
Overall risk after controls2 MModeratethe highest rating after controls
8 more job steps, from Arrival on-site & assess onsite conditions to Emergency response