Construction Site Amenities Cleaning

SWMS · SWMS-10609

  • 10 job steps
  • Version 5
  • Cleaning
  • Reads on any phone

This Construction Site Amenities Cleaning Safe Work Method Statement (SWMS) covers the hazards and controls for cleaning tasks at construction site amenities, to help keep the work safe and efficient.

It covers 10 job steps, from planning and arriving on site to travel on-site, work area set-up, the environment, housekeeping, manual tasks, sweeping, mopping and surface cleaning, completion and emergency response.

It includes controls for manual tasks, contaminated materials and sharps, hazardous chemicals, and work from platform ladders.

It suits cleaning service providers, property management firms, construction and renovation contractors and facility management services.

Preview of the Construction Site Amenities Cleaning SWMS

Construction Site Amenities Cleaning

SWMSVersion 5
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile Plant
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/Review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Act, regulations, codes of practice references

None listed.

Personal Protective Equipment (PPE)

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Eye Protection
  • Hand Protection
  • Protective Clothing
  • Breathing Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Planning

    • Hazard

      Fatigue

      Unauthorised access

      Insecure workplace

      Before controls3 High
      Controls
      • Out-of-hours / night work:

        • Allow adequate meal breaks for workers; especially if they have worked during part of the day, they will need time to rest & recover sufficiently to work safely into the evening/night

        • Do not schedule full double shifts for workers as worker fatigue increases the risk of incidents

        • Workers have access to:

          • Suitable amenities (toilets/wash facilities/drinking water)

          • Sufficient lighting (including parking areas)

          • Air conditioning, heating and mechanical ventilation if required

          • Emergency exits

          • Safe area for parking/unloading equipment – protected from rain

      • Additional security personnel on-site to ensure no unauthorised access by the general public while work is being performed

        • No worker should work alone on the site at night.

      After controls2 Moderate
      Responsible
      • Supervisorto ensure all planning and scheduling is followed
    • Hazard

      Infection Disease Allergic reaction

      Before controls3 High
      Controls
      • Ensure vaccinations (such as Hepatitis B, tetanus.) are offered for staff.

      • people with known allergic responses should consult a doctor and ensure appropriate kit is available at all times (Including EpiPen - in date).

      After controls2 Moderate
      Responsible
      • Supervisorto ensure all planning and scheduling is followed
    • Hazard

      Emergency

      Before controls4 Acute
      Controls
      • Avoid people working alone, use a buddy system to provide immediate support

      • Have a reliable communication system in place and test regularly

        • Emergency procedures:

          • Emergency contacts (enter numbers here)

          • Building security (enter numbers here)

          • Nearest medical facility (enter the address here)

          • Location of fire protection equipment

          • Emergency exits and assembly areas.

      After controls2 Moderate
      Responsible
      • Supervisorto ensure all planning and scheduling is followed

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

9 more job steps, from Arrival on-site & assess onsite conditions to Emergency response

Each with its hazards, risk ratings and controls, plus your crew's sign-on.

Preview as

How it reads in a browser

Get this template

Sign up free, then choose how you'd like it. Your company details fill in for you.

  • Included in paid plans

    Use template credits from your plan. This one costs 1.

    Compare plans and prices
  • Buy it once

    $89.95 paid once, and it's yours to keep. Works on the free plan too.

No card needed to sign up. Early access members get 30% off any plan.

What it covers

10 job steps

  1. PlanningPlan shifts, amenities, security and emergency arrangements for out-of-hours work
  2. Arrival on-site & assess onsite conditionsAssess the site conditions on arrival to identify hazards
  3. Travel on-siteTravel on-site safely around vehicles, mobile plant and pedestrians
  4. Work area set-upSet up the work area and keep unauthorised people out
  5. EnvironmentControl the environmental impact of cleaning activities
  6. HousekeepingKeep the work area tidy and free of slip and trip hazards
  7. Manual tasksReduce the risks of manual tasks
  8. Sweeping, mopping & surface cleaningSweep, mop and clean surfaces, handling contaminated materials and chemicals safely
  9. On completionConclude the work and secure the site
  10. Emergency responseRespond to emergencies

Hazards it covers

Reviews

No reviews yet.

See all

How templates work

Try it before you pay.

  1. Preview free

    Every template's job steps, hazards and first task are open to read. No sign-up.

  2. Try the editor

    Tailor a demo SWMS with your company, job and site, on a computer or your phone.

  3. Sign up free

    Your details and logo carry over. This template opens already filled in.

  4. Use a credit or buy once

    Paid plans include template credits every month. Or buy this one to keep.