Concrete Scanning

SWMS · SWMS-10422

  • 8 job steps
  • Version 3
  • Concreting
  • Reads on any phone

This Concrete Scanning Safe Work Method Statement (SWMS) covers the hazards and controls associated with scanning concrete. It includes additional controls for electrical equipment, elevated levels, slips, trips and falls, hazardous manual tasks, outdoor work, and environmental considerations.

It covers 8 job steps: checking weather conditions and preparing, arriving on-site and assessing on-site conditions, environment, housekeeping, manual tasks, concrete scanning, on completion and emergency response.

It identifies the high-risk construction work of mobile plant movement and work with a risk of a fall from 2 m or more, with detailed control measures for a wide range of potential hazards.

It suits businesses and workers in construction, renovation and maintenance projects where concrete scanning is required, including site supervisors, scanning technicians and safety officers.

Preview of the Concrete Scanning SWMS

Concrete Scanning

SWMSVersion 3
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile Plant
  • Falls

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold Points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/Review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • High Visibility

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Check weather conditions & prepare

    • Hazard

      Extreme weather

      Before controls3 High
      Controls
      • Check weather conditions – do not work in extreme conditions

      • Reschedule works to work in more moderate temperatures.

      After controls2 Moderate
      Responsible
      • Supervisorto maintain awareness of weather conditions
      • Operatorto follow controls
    • Hazard

      Hyperthermia, Hypothermia

      Before controls3 High
      Controls
      • Ensure that workers trained to recognise the symptoms of hyperthermia and hypothermia

      • Hot conditions. Ensure:

        • Suitable protective clothing

        • Sun brim on hard hats

        • Safety glasses - UV rated

        • Use 30+ sunscreen on exposed skin

        • Adequate drinking water

        • Access to shade on breaks

        • Adequate breaks.

      • Cold conditions. Ensure:

        • Schedule warm-up breaks

        • Hold breaks inside

        • Dress warmly in layers

        • Stay dry (wet clothing chills the body rapidly)

        • Workers must get out of the cold as soon as they can if starting to feel symptoms

        • Alcohol, cigarettes, caffeine and certain medications increase susceptibility to cold.

      After controls2 Moderate
      Responsible
      • Supervisorto maintain awareness of weather conditions
      • Operatorto follow controls

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

7 more job steps, from Arrival on-site & assess onsite conditions to Emergency response

Each with its hazards, risk ratings and controls, plus your crew's sign-on.

Preview as

How it reads in a browser

Get this template

Sign up free, then choose how you'd like it. Your company details fill in for you.

  • Included in paid plans

    Use template credits from your plan. This one costs 1.

    Compare plans and prices
  • Buy it once

    $89.95 paid once, and it's yours to keep. Works on the free plan too.

No card needed to sign up. Early access members get 30% off any plan.

What it covers

8 job steps

  1. Check weather conditions & prepareCheck the weather and prevent heat and cold illness before starting.
  2. Arrival on-site & assess onsite conditionsPosition the vehicle safely and assess the site on arrival.
  3. EnvironmentLimit the environmental impact of the work.
  4. House keepingKeep the work area clean and free of trip hazards.
  5. Manual tasksAvoid musculoskeletal injuries from manual tasks.
  6. Concrete scanningCheck the scanner and work safely at height while scanning.
  7. On completionSign out and leave the site by safe routes.
  8. Emergency responseRespond to injuries, fatalities or environmental damage.

Hazards it covers

Reviews

No reviews yet.

See all

How templates work

Try it before you pay.

  1. Preview free

    Every template's job steps, hazards and first task are open to read. No sign-up.

  2. Try the editor

    Tailor a demo SWMS with your company, job and site, on a computer or your phone.

  3. Sign up free

    Your details and logo carry over. This template opens already filled in.

  4. Use a credit or buy once

    Paid plans include template credits every month. Or buy this one to keep.