Concrete Waffle Pod Raft System

SWMS · SWMS-10309

  • 17 job steps
  • Version 8
  • Concreting
  • Reads on any phone

This Concrete Waffle Pod Raft System Safe Work Method Statement (SWMS) guides the safe handling, delivery and placement of wet concrete into a waffle pod raft system. It covers the hazards and controls for the work.

It covers 17 job steps, from training on respirable crystalline silica and preparing for the weather to delivering materials, subgrade preparation, placing waffle pods, setting steel and formwork, placing and finishing concrete, fuelling small engines, completion and emergency response.

It includes controls for high-risk construction work around mobile plant, traffic, overhead power lines and underground services, and for electrical equipment, slips, trips and falls, hazardous substances and manual tasks.

It suits construction teams, site supervisors and safety officers on waffle pod raft projects, from ground workers to project managers.

Preview of the Concrete Waffle Pod Raft System SWMS

Concrete Waffle Pod Raft System

SWMSVersion 8
Company doing the work
[Company]
Business contact
—
Phone #
—
Responsible person (for monitoring SWMS and work)
—
Signature
—
Date
—
Contact phone #
—
Principal contractor (PC)
[Principal contractor]
PC address
—
PC phone #
[PC phone]
Date SWMS provided to PC
—
Job site address
[Site address]
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile PlantWork in an area where there is any movement of powered mobile plant
  • Traffic CorridorsWork on, in or adjacent to a road, railway, shipping lane or other traffic corridor in use by traffic other than pedestrians
  • Energised ElectricalWork on or near energised electrical installations or services
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere

Planning and preparation

Planning

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training and licences

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Eye Protection
  • Hand Protection
  • Protective Clothing
  • Sun Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Provide training on the health effects associated with RCS

    • Hazard

      Exposure to respirable crystalline silica (RCS) – dust inhalation

      Before controls3 High
      Controls
      • Training and Information provided to workers on RCS should include:

        • Identification of RCS dust through Safety Datasheet (SDS) or labels

        • Dust exposure prevention strategies

        • Checking controls are working and using them

        • When and how to use any respiratory protective equipment provided and what to do if something goes wrong (Including worker respirator fit and check processes).

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

16 more job steps, from Check weather conditions & prepare to Emergency response

Each with its hazards, risk ratings and controls, plus your crew's sign-on.

Preview as

How it reads in a browser

Get this template

Sign up free, then choose how you'd like it. Your company details fill in for you.

  • Included in paid plans

    Use template credits from your plan. This one costs 1.

    Compare plans and prices
  • Buy it once

    $89.95 paid once, and it's yours to keep. Works on the free plan too.

No card needed to sign up. Early access members get 30% off any plan.

What it covers

17 job steps

  1. Provide training on the health effects associated with RCSTrain workers on the health effects of RCS
  2. Check weather conditions & prepareCheck the weather and prepare for hot and cold conditions
  3. Arrival on-site & assess onsite conditionsPark safely, report to the supervisor and assess the site
  4. Work area set-upBarricade the work area and keep unauthorised people out
  5. EnvironmentControl noise, waste, spills and other environmental impacts
  6. House keepingKeep the work area clean and free of trip hazards
  7. Manual tasksLift and handle materials safely
  8. Delivering materials - Subgrade preparation - Concrete deliveryDeliver materials and concrete clear of power lines, plant and traffic
  9. Working with powered & non-powered toolsInspect and use powered and hand tools safely
  10. Setting out/profiling building linesLocate services, cap pegs and use visible string lines
  11. Subgrade preparationLocate underground services and keep clear of plant
  12. Waffle pod placementCut and place waffle pods and keep fire away from them
  13. Setting steel & formworkCut and tie steel and set formwork safely
  14. Placing concrete & finishPlace and finish concrete around trucks, pumps and trowelling machines
  15. Fuelling small engines on-siteRefuel small engines safely
  16. On completionInspect equipment, pack up leads and sign out
  17. Emergency responseCall 000 and follow the site emergency procedures

Hazards it covers

Reviews

No reviews yet.

See all

How templates work

Try it before you pay.

  1. Preview free

    Every template's job steps, hazards and first task are open to read. No sign-up.

  2. Try the editor

    Tailor a demo SWMS with your company, job and site, on a computer or your phone.

  3. Sign up free

    Your details and logo carry over. This template opens already filled in.

  4. Use a credit or buy once

    Paid plans include template credits every month. Or buy this one to keep.