Generator Portable
- Company doing the work
- [Company]
- Business contact and phone
- —
- Responsible person (for monitoring SWMS and work)
- —
- Responsible person's phone
- —
- Responsible person's signature
- —
- Date signed
- —
- Principal Contractor (PC)
- [Principal contractor]
- PC Address
- —
- PC phone
- [PC phone]
- Date SWMS provided to PC
- —
- Job Site Address
- [Site address]
- Part of a construction project
- —
Site management plan
If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.
High-risk construction work
This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)
- Hazardous Atmosphere
Planning and preparation
Planning/Preparation
Liaise with Principal Contractor to identify on-site safety systems and procedures
Establish supervisory and communication arrangements
Principal contractor to confirm emergency response procedures are in place.
Hold points
Hold points identified and signed off before continuing work. (specify the hold points)
Training/Licence
All workers to have a General Construction Induction Card
Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.
Trained First Aider on site
All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.
Worker duties and responsibilities
Fit condition for work, i.e., no signs of fatigue, alcohol or drugs
Attend all site inductions/briefings
Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)
Only carry out work related to the contract
Inspect completed work and report possible safety, environmental and quality matters to the supervisor.
Monitor/Review
All people involved in the task must have this SWMS communicated to them before work commences
SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident
If additional site hazards identified, review this SWMS and amend control measures to suit
People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP
Give the principal contractor a copy of the revised SWMS
The site supervisor to monitor works against the controls stated in this SWMS
SWMS must be kept on-site and made available for inspection or review
Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident
Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.
Site-specific notes
Legislation and codes of practice
None listed.
Personal protective equipment
- Foot Protection
Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.
Job steps, hazards and controls
- Work activity
Transporting the generator to/from sites
- Hazard
Crush injuries
Before controls4 AcuteControlsTowing a trailer-mounted generator:
Block wheels to prevent accidental movement during coupling and uncoupling
Hitch generator to the vehicle, check coupling and safety chains are secure
Plugin rear warning (indicator) lamps lead to the socket on the vehicle
Check that the warning lights are operating correctly
Ensure that the jockey wheel and stabiliser legs raised and secured
Check delivery location is agreed on and suitable
Do not drive at an excessive speed when towing.
After controls2 ModerateResponsible- Supervisorsto check all controls in place and followed
- Workersto follow controls and make supervisor aware of any issues
- Hazard
Fire / explosion
Before controls3 HighControlsSecure fuel containers outside of the main cabin.
Ensure the fuel valve on the generator is in the closed position.
Fuel:
Minimum quantities stored
Containers clearly labelled and legible
Fire protection equipment accessible, tested and tagged.
After controls2 ModerateResponsible- Supervisorsto check all controls in place and followed
- Workersto follow controls and make supervisor aware of any issues
- Hazard
Projectile / Moving objects
Before controls3 HighControlsSmaller portable generators must be transported in a trailer, or tray of utility – not inside the cabin of the vehicle
Secure the generator in the vehicle tray with lashing/restraint equipment to prevent movement during transport
Ensure that all people stand clear of potential fall zones during loading/unloading the generator.
After controls2 ModerateResponsible- Supervisorsto check all controls in place and followed
- Workersto follow controls and make supervisor aware of any issues
- Hazard
Musculoskeletal (MSD) injuries
Before controls3 HighControlsUse safe manual handling techniques for loading and unloading the generator
Do not attempt to lift the machine by yourself. Use lifting equipment to move the generator where required. If using team handling:
Ensure all people matched physically
One person directs the move
Move planned and rehearsed
Team handling only used where better means to move equipment (trolley) are not practicable.
After controls2 ModerateResponsible- Supervisorsto check all controls in place and followed
- Workersto follow controls and make supervisor aware of any issues
IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute
Overall risk after controls2 MModeratethe highest rating after controls
8 more job steps, from Arrival on-site & assess onsite conditions to Emergency response