Electric Fusion - Poly Pipe Butt Welding (PPW)

SWMS · SWMS-10201

  • 11 job steps
  • Version 3

This SWMS sets out the job steps, hazards and controls for welding polyethylene pipe by electric fusion, using the butt welding technique.

It takes your crew through each step, from arriving on site, checking the weather and setting up the work area to working near powered mobile plant, pipe facing, heating and welding, weld inspection, completion and emergency response.

It suits businesses and contractors that weld polyethylene pipe, particularly where mobile plant is moving or the atmosphere may be contaminated, and the supervisors and workers who carry out the high-risk construction work.

Written by SafetyDocs safety experts, who have been writing safety documents since 2004.

See its own page

Preview of the Electric Fusion - Poly Pipe Butt Welding (PPW) SWMS

Electric Fusion - Poly Pipe Butt Welding (PPW)

SWMSVersion 3
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following 'High-Risk Construction Work' (HRCW - identified in the Job Task column):

  • Mobile Plant
  • Hazardous Atmosphere

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers are trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/Review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards are identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

(add notes specific to this site)

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Head Protection
  • Eye Protection
  • Hand Protection
  • Protective Clothing
  • Breathing Protection
  • Sun Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Arrival on-site & assess onsite conditions

    • Hazard

      Personal injury, property damage &/or environmental incident

      Before controls3 High
      Controls
      • The vehicle should be positioned in a safe location, clear of traffic/vehicles/pedestrians during equipment delivery and materials removal (deploy physical barriers, caution signs as necessary)

      • Do not park illegally

      • Identify and obey all safety-related signage (check site entry requirements)

      • Report to Site Supervisor

      • Ensure site-specific induction undertaken

      • Assess mobile phone reception

      • The work site is exactly as detailed in the Terms of the Agreement or contract

      • Complete a JSA specifying the control measures of unanticipated hazards.

      After controlsNot rated
      Responsible
      • Supervisorto check the site and conduct JSA where necessary

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

10 more job steps, from Check weather conditions & prepare to Emergency response

Each with its hazards, risk ratings and controls, plus your crew's sign-on.

Preview as

How it reads in a browser

Get this system

Sign up free, then choose how you'd like it. Every document goes into your Library, in a folder named for the pack.

  • Included in paid plans

    Use template credits from your plan. This one costs 20.

    Compare plans and prices
  • Buy it once

    $999.90 paid once, and it's yours to keep. Works on the free plan too.

No card needed to sign up. Early access members get 30% off any plan.

What it covers

11 job steps

  1. Arrival on-site & assess onsite conditionsPark safely, report to the supervisor and check the site
  2. Check weather conditions & prepareCheck the weather and protect workers from heat and cold
  3. EnvironmentControl noise, waste, spills and other environmental impacts
  4. Work area set-upSet up the exclusion zone, weather protection, fire equipment and ventilation
  5. Working near powered mobile plantKeep clear of powered mobile plant and follow the TMP
  6. House keepingKeep the work area clean and free of trip hazards
  7. Manual tasksLift and move materials safely
  8. Electric & Polyethylene Pipe Welding (PPW)Face, heat and weld the pipe safely
  9. Conduct visual inspection of weldInspect each weld bead for size, height and faults
  10. On completionRemove barricades, unload pipes, pack up leads and sign out
  11. Emergency responseCall 000, follow emergency procedures and give first aid

Hazards it covers

How templates work

Try it before you pay.

  1. Preview free

    Every template's job steps, hazards and first task are open to read. No sign-up.

  2. Try the editor

    Tailor a demo SWMS with your company, job and site, on a computer or your phone.

  3. Sign up free

    Your details and logo carry over. This template opens already filled in.

  4. Use a credit or buy once

    Paid plans include template credits every month. Or buy this one to keep.