Mini Crane

SWMS · SWMS-10598

  • 16 个工作步骤
  • 版本 3

This SWMS covers the hazards and controls for operating a mini crane on construction sites. Mini cranes are compact and manoeuvrable, which makes them useful where space is limited or a larger crane is impractical.

It takes the crew through 16 job steps, from planning, delivery and set-up to crane placement, inspecting load equipment, the pre-lift assessment, crane operation, maintenance, re-fuelling and emergency response.

It also covers the high-risk construction work controls, with precautions for working near power lines, slips, trips and falls, manual tasks and environmental considerations.

It suits construction professionals who handle compact lifting equipment in a range of construction settings.

查看单独页面

Mini Crane SWMS 预览

Mini Crane

SWMSVersion 3

Document details

Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal contractor (PC)
[Principal contractor]
PC address
—
PC phone
[PC phone]
Date SWMS provided to PC
—
Job site address
[Site address]
Business contact phone
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile Plant
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere
  • Traffic CorridorsWork carried out adjacent to a road, railway or shipping lane, traffic corridor

Planning and preparation

Planning/preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Head Protection
  • Eye Protection
  • Hand Protection
  • Protective Clothing
  • Breathing Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Planning

    • Hazard

      Contact with overhead electric lines

      Before controls4 Acute
      Controls
      • Liaise with electrical entities where necessary regarding the supply of electricity and control measures for working around existing power supply (e.g. de-energising powerlines) including loading bays and site access.

      After controls2 Moderate
      Responsible
      • Supervisor
    • Hazard

      Inadequate crane team

      Before controls3 High
      Controls
      • Assess the size and complexity of the work to be undertaken

      • Determine the crane crew required for the task. Consider:

        • Number of operators and doggers required

        • Number of riggers required for the activities

        • Whether a trained safety observer is required for maintaining electrical exclusion zones

        • Whether a crane coordinator should be appointed.

      After controls2 Moderate
      Responsible
      • Supervisor
    • Hazard

      Rollover

      Before controls4 Acute
      Controls
      • Verify the work ground/floor is suitable for the particular machine

      • Ensure the ground/floor is safe and approved for use by a competent person.

      After controls2 Moderate
      Responsible
      • Supervisor
    • Hazard

      Lack of training resulting in injuries & fatalities

      Before controls4 Acute
      Controls
      • All operators have the appropriate Heavy Vehicle licence for mobile crane

      • The operator holds a valid certificate to operate such a crane – e.g. C2 for cranes with a capacity up to 20 tonnes; C6 up to 60 tonnes; C1 up to 100 tonnes, and CO greater than 100 tonnes

        • Operation: High-Risk Work Licence

          • E.g. Crane: Slewing mobile crane—with a capacity of up to 20 tonnes

          • E.g. Dogman: Dogging

          • E.g. Rigger: Basic rigging - Intermediate rigging - Advanced rigging

      • Ensure all relevant workers have undertaken training and/or received instruction in the use of control measures. Include:

        • Appropriate mathematical procedures for estimation and measurement of loads

        • Knowledge of types of crane and their individual functions

        • Types of lifting equipment and slinging techniques for use.

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

还有 15 个工作步骤,从“Delivery, set-up & removal of the crane”到“Emergency response”

每一步都有危险、风险等级和控制措施,另附工人签到。

预览方式

在浏览器中的样子

获取这个体系

免费注册,然后选择获取方式。每份文件都会放进你的模板库,存在以套装命名的文件夹里。

  • 付费套餐包含

    使用套餐中的模板额度。这一份需要 20 个额度。

    比较套餐和价格
  • 单独购买

    $999.90 一次付清,永久归你。免费套餐也能用。

注册无需银行卡。抢先体验会员购买任何套餐都可享 30% 折扣。

涵盖内容

16 个工作步骤

  1. PlanningPlan the electrical safety and the make-up of the crane team
  2. Delivery, set-up & removal of the craneTransport the crane safely and set it up securely
  3. Work area set-upPrepare the work area with safety in mind
  4. EnvironmentManage the environmental impact of the work
  5. House keepingKeep the work area clean and safe
  6. Manual tasksPrevent musculoskeletal injuries
  7. Establish a communication systemSet up clear communication for crane operations
  8. Crane placementPosition the crane safely, especially near power lines
  9. Select and inspect load equipmentInspect the load equipment and check it is safe to use
  10. Pre-lift AssessmentAssess the load and the conditions before lifting
  11. Crane pre-start checkCheck the crane is in safe operating condition
  12. Crane OperationOperate the crane safely to prevent accidents
  13. Maintenance on-siteCarry out maintenance safely on site
  14. Re-fuelling on siteRe-fuel safely on site
  15. On completionLeave the site safe and secure after the work
  16. Emergency responsePrepare workers to respond to an emergency

涵盖的危险

模板如何使用

在付款前先试用。

  1. 免费预览

    每个模板的工作步骤、危险和第一项任务都可以直接阅读,无需注册。

  2. 试用编辑器

    在电脑或手机上,用你的公司、工作和工地信息修改一份演示 SWMS。

  3. 免费注册

    你的信息和标志都会带过去。这个模板打开时已经填好。

  4. 使用额度或单独购买

    付费套餐每月都包含模板额度。也可以单独购买这一份,永久保留。