Erecting Suspended Powered Scaffolds

SWMS · SWMS-10538

  • 16 job steps
  • Version 4
  • Working at Height
  • Reads on any phone

This Erecting Suspended Powered Scaffolds Safe Work Method Statement (SWMS) outlines the safety measures for setting up and taking down suspended powered scaffold systems, like swing stages. It details the potential hazards and control measures needed for safe operations.

It covers 16 job steps: planning, implementing a falls emergency rescue plan, arriving on-site and assessing conditions, work area set-up, environment, checking the weather, housekeeping, manual tasks, working with powered and non-powered tools, pre-inspecting system components and assembling the platform, installing electrical cabling for hoist operations, setting up supports and anchors, commissioning and handover, dismantling, on completion and emergency response.

It includes height safety measures, with guidelines for working at height, the use of fall protection systems and secure anchoring methods.

It suits scaffolders, construction managers, safety officers and site supervisors involved in erecting and dismantling suspended powered scaffolds.

Preview of the Erecting Suspended Powered Scaffolds SWMS

Erecting Suspended Powered Scaffolds

SWMSVersion 4

Document details

Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site Management Plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-Risk Construction Work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Gas MainsPressurised gas distribution mains or piping
  • Hazardous Lineschemical, fuel or refrigerant lines
  • Energised Electricalenergised electrical installations or services
  • FallsInvolves a risk of a person falling from 2m or more, including work on telecommunications towers

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold Points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/Review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-Specific Notes

Legislation and codes of practice

None listed.

Personal Protective Equipment (PPE)

  • Foot Protection
  • High Visibility
  • Head Protection
  • Hand Protection
  • Protective Clothing
  • Sun Protection
  • Safety Harness

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Planning

    • Hazard
      • Incorrect system design

      • System collapse

      Before controls4 Acute
      Controls
      • The suspended scaffold system must be designed and documented by a competent person, e.g. Engineer. (Designer/manufacturer instructions must be supplied with the scaffold system.)

      • Every area of design for a suspended scaffold system must receive a formal sign-off from a competent person, including:

        • Support/anchor equipment

        • Supporting structure assessed (statement of assessment provided)

        • Suspended equipment

        • Wire, ropes and chains

        • Fall restraint equipment.

      • Purpose-built suspended scaffolds must:

        • Be clearly marked with the brand name, model number, and serial number

        • Be clearly marked with its capacity and intended use

        • Clearly display the mass in kg. of any counterweights.

      • A detailed design and erection plan must be in place for each new site

      • The design plan must take into account the following:

        • Design specifications of the scaffold

        • Limitations of the support structure (rooftops, parapets etc.)

        • Maximum operational wind speed or lateral forces the system is exposed to during erection or operation

        • Activities while on the scaffold, e.g. water, pressure blasting

        • Voltage drop for longer runs on electrically powered hoists (Ensure coordination between the electrical and scaffolding contractors to ensure the correct voltage levels provided).

      • Ensure all components meet relevant Standards.

      After controls2 Moderate
      Responsible
      • Supervisorto confirm the system design is signed off

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

15 more job steps, from Implement a Falls Emergency Rescue Plan to Emergency response

Each with its hazards, risk ratings and controls, plus your crew's sign-on.

Preview as

How it reads in a browser

Get this template

Sign up free, then choose how you'd like it. Your company details fill in for you.

  • Included in paid plans

    Use template credits from your plan. This one costs 1.

    Compare plans and prices
  • Buy it once

    $89.95 paid once, and it's yours to keep. Works on the free plan too.

No card needed to sign up. Early access members get 30% off any plan.

What it covers

16 job steps

  1. PlanningPlan the suspended scaffold system and have its design signed off
  2. Implement a Falls Emergency Rescue PlanHave a falls emergency rescue plan in place
  3. Arrival on-site & assess onsite conditionsAssess the site on arrival and complete a JSA where necessary
  4. Work area set-upSecure the work area and set up exclusion zones
  5. EnvironmentControl noise, waste, run-off, vehicle movement and animals on site
  6. Check weather conditions & prepareCheck the weather and prepare for hot or cold conditions
  7. House keepingKeep the work area clean and clear of trip hazards
  8. Manual tasksHandle materials and equipment to prevent musculoskeletal injury
  9. Working with powered & non-powered toolsUse powered and non-powered tools safely
  10. Pre-inspect system components & assembling the platformInspect the system components and assemble the platform
  11. Installation of electrical cabling for hoist operationsInstall the electrical cabling for the hoists
  12. Setting up supports & anchorsSet up the supports and anchors
  13. Commission & handoverTest, inspect and hand over the scaffold
  14. DismantlingDismantle the scaffold in a systematic and progressive way
  15. On completionSecure the site and store the equipment on completion
  16. Emergency responseRespond to injuries and emergencies and rescue a suspended worker

Hazards it covers

Reviews

No reviews yet.

See all

How templates work

Try it before you pay.

  1. Preview free

    Every template's job steps, hazards and first task are open to read. No sign-up.

  2. Try the editor

    Tailor a demo SWMS with your company, job and site, on a computer or your phone.