Workbox
- Company doing the work
- [Company]
- Business contact
- —
- Business contact phone
- —
- Responsible person (for monitoring SWMS and work)
- —
- Responsible person's phone
- —
- Responsible person's signature
- —
- Date signed
- —
- Principal contractor (PC)
- [Principal contractor]
- PC address
- —
- PC phone
- [PC phone]
- Date SWMS provided to PC
- —
- Job site address
- [Site address]
- Part of a construction project
- —
Site management plan
If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.
High-risk construction work
This work activity involves the following “High-Risk Construction Work” (HRCW – identified in the Job Task column)
- Mobile PlantMobile plant movement
- FallsInvolves a risk of a person falling from 2m or more, including work on telecommunications towers
- Gas Mains
- Hazardous Lines
- Energised Electrical
Working with a risk of a fall over 2 metres
The fall from height hierarchy of control level considered when establishing controls:
- L1Work on the ground or solid construction, not chosen
- L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
- L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
- L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
- L5Implement administrative controls, e.g. signage or instruction, not chosen
No level has been chosen yet.
Planning and preparation
Planning
Liaise with Principal Contractor to identify on-site safety systems and procedures
Establish supervisory and communication arrangements
Principal contractor to confirm emergency response procedures are in place.
Hold points
Hold points identified and signed off before continuing work. (specify the hold points)
Training and licences
All workers to have a General Construction Induction Card
Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.
Trained First Aider on site
All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.
Worker duties and responsibilities
Fit condition for work, i.e., no signs of fatigue, alcohol or drugs
Attend all site inductions/briefings
Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)
Only carry out work related to the contract
Inspect completed work and report possible safety, environmental and quality matters to the supervisor.
Monitoring and review
All people involved in the task must have this SWMS communicated to them before work commences
SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident
If additional site hazards identified, review this SWMS and amend control measures to suit
People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP
Give the principal contractor a copy of the revised SWMS
The site supervisor to monitor works against the controls stated in this SWMS
SWMS must be kept on-site and made available for inspection or review
Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident
Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.
Site-specific notes
Legislation and codes of practice
None listed.
Personal protective equipment (PPE)
- Foot Protection
- High Visibility
- Head Protection
- Hand Protection
- Protective Clothing
- Sun Protection
- Safety Harness
Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.
Job steps, hazards and controls
- Work activity
Planning
- Hazard
Contact with overhead electric lines
Before controls4 AcuteControlsLiaise with electricity supply authorities regarding control measures for working near overhead electric lines. In general:
3m above, either side and below power lines is No Go Zone
3-6.4m of power lines a Spotter is required
Further than 6.4m of electric lines is an open area
No work to be conducted within a 10m radius of SWER transformer.
Note: Authorised people may be permitted to work within minimum safe distance zones for jobs such as tree clearing work, provided requirements of the State Energy Authority and owner of the electric line are followed.
After controls2 ModerateResponsible- Supervisorto liaise with electricity supply authorities & workbox maintenance
- Hazard
Equipment failure
Before controls3 HighControlsEnsure all servicing and maintenance is performed by suitably licensed, qualified & competent people, as per legislative requirements, and manufacturer’s recommendations
Inspecting and testing workbox must include the:
Annual inspections
Regular weekly, monthly inspection and maintenance
Daily Pre-operational inspections and checks
Inspections and maintenance should include:
The effective functioning of safety devices and lifting equipment
Detailed visual inspection check for corrosion or damage (wear, cracks)
Detailed examination of critical areas for evidence of cracking
Emergency and safety devices (anchor points, harnesses)
Signage, including warning signs and decals
Extra items nominated in the manufacturer’s instructions
All replacement parts should be identical or equivalent to the original parts or components
Maintain and complete the logbook of service and maintenance history as required
Inspection records should include a statement from the appropriate competent person confirming the workbox has been inspected and is safe to use.
After controls2 ModerateResponsible
IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute
Overall risk after controls2 MModeratethe highest rating after controls
12 more job steps, from Implement a Falls Emergency Rescue Plan to Emergency response
Each with its hazards, risk ratings and controls, plus your crew's sign-on.