  • 19 job steps
  • Version 3

This SWMS covers the setup and operation of a self-erecting crane on construction sites. It sets out the safety controls for each job step, with the hazards, risk ratings and who is responsible.

It takes your crew through 19 job steps, from crane lift planning, road operation and arrival on site to crane placement, erecting the crane, load equipment, pre-lift assessment, crane operation, workboxes, maintenance, re-fuelling, completion and emergency response.

It addresses high-risk construction work such as mobile plant movement and energised electrical installations, and suits construction managers, safety officers and crane operators on projects that use self-erecting cranes.

Written by SafetyDocs safety experts, who have been writing safety documents since 2004.

See its own page

Preview of the Crane Self-Erecting SWMS

Crane Self-Erecting

SWMSVersion 3

Document details

Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW – identified in the Job Task column)

  • Mobile PlantMobile plant movement
  • Gas MainsPressurised gas distribution mains or piping
  • Hazardous Lineschemical, fuel or refrigerant lines
  • Energised Electricalenergised electrical installations or services
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere

Planning and preparation

Planning

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

Hold points identified and signed off before continuing work. (specify the hold points)

Training and licences

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Head Protection
  • Eye Protection
  • Hand Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Crane lift planning

    • Hazard

      Contact with overhead electric lines

      Before controls4 Acute
      Controls
      • Liaise with electrical entities where necessary regarding the supply of electricity and control measures for working around existing power supply (e.g. de-energising powerlines) including loading bays and site access.

      After controls2 Moderate
      Responsible
      • Supervisor
    • Hazard

      Inadequate crane team

      Before controls3 High
      Controls
      • Assess the size and complexity of the work to be undertaken

        Determine the crane crew required for the task. Consider:

        • Number of operators and doggers required

        • Number of riggers required for the activities

        • Whether a trained safety observer is required for maintaining electrical exclusion zones

        • Whether a crane coordinator should be appointed.

      After controls2 Moderate
      Responsible
      • Supervisor
    • Hazard

      Lack of training resulting in injuries & fatalities

      Before controls4 Acute
      Controls
      • All operators have the appropriate Heavy Vehicle licence for mobile crane

      • The operator holds a valid certificate to operate such a crane – e.g. C2 for cranes with a capacity up to 20 tonnes; C6 up to 60 tonnes; C1 up to 100 tonnes, and C0 greater than 100 tonnes

        • Operation – High-Risk Work Licence

          • E.g. Crane – Self-erecting tower crane

          • E.g. Dogman – Dogging

          • E.g. Rigger – Basic rigging - Intermediate rigging - Advanced rigging

      • Ensure relevant workers have undertaken training and received instruction in the use of control measures. Include:

        • Appropriate mathematical procedures for estimation and measurement of loads

        • Knowledge of types of crane and their functions

        • Use of lifting equipment and slinging techniques

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

18 more job steps, from Road operation to Emergency response

Each with its hazards, risk ratings and controls, plus your crew's sign-on.

Preview as

How it reads in a browser

Get this value pack

Sign up free, then choose how you'd like it. Every document goes into your Library, in a folder named for the pack.

  • Included in paid plans

    Use template credits from your plan. This pack costs 6 instead of 7.

    Compare plans and prices
  • Buy it once

    $539.70 $629.65 paid once, and it's yours to keep. Works on the free plan too.

No card needed to sign up. Early access members get 30% off any plan.

What it covers

19 job steps

  1. Crane lift planningPlan the lift, the crane crew and the licences needed
  2. Road operationInspect the crane before travel and follow the road rules
  3. Arrival on-site & assess onsite conditionsAssess the site, report to the supervisor and complete the induction
  4. EnvironmentManage noise, waste, fuels and other environmental impacts
  5. Crane placementPlace the crane, set up exclusion zones and watch for plant movement
  6. Erecting the craneErect the crane to the manufacturer’s specifications
  7. House keepingKeep the work area clean and clear of trip hazards
  8. Manual tasksHandle materials and equipment safely to prevent injury
  9. Establish a communication systemSet up communication between the crane operator and ground workers
  10. Select and inspect load equipmentSelect and inspect slings, chains, hooks and tag lines
  11. Pre-lift AssessmentAssess the load and the wind before lifting
  12. Crane pre-start checkCarry out the pre-start checks on the crane
  13. Crane OperationOperate the crane and handle the load safely
  14. WorkboxesUse the workbox safely
  15. Daily shutdown and storageShut down and store the crane and equipment
  16. Maintenance on-siteMaintain the crane safely on site
  17. Re-fuelling on siteRe-fuel safely and prevent fire
  18. On completionClear the site and dismantle the crane safely
  19. Emergency responseRespond to an emergency

Hazards it covers

How templates work

Try it before you pay.

  1. Preview free

    Every template's job steps, hazards and first task are open to read. No sign-up.

  2. Try the editor

    Tailor a demo SWMS with your company, job and site, on a computer or your phone.

  3. Sign up free

    Your details and logo carry over. This template opens already filled in.

  4. Use a credit or buy once

    Paid plans include template credits every month. Or buy this one to keep.