Formwork Decks-Columns-Stairs
Document details
- Company doing the work
- [Company]
- Business contact
- —
- Business contact phone
- —
- Responsible person (for monitoring SWMS and work)
- —
- Responsible person's phone
- —
- Responsible person's signature
- —
- Date signed
- —
- Principal contractor (PC)
- [Principal contractor]
- PC address
- —
- PC phone
- [PC phone]
- Date SWMS provided to PC
- —
- Job site address
- [Site address]
- Part of a construction project
- —
Site management plan
If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.
High-risk construction work
This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)
- Mobile PlantMobile plant movement
- Structural AlterationsStructures or buildings involving structural alterations or repairs that require temporary support to prevent collapse
- FallsInvolves a risk of a person falling from 2m or more, including work on telecommunications towers
Working with a risk of a fall over 2 metres
The fall from height hierarchy of control level considered when establishing controls:
- L1Work on the ground or solid construction, not chosen
- L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
- L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
- L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
- L5Implement administrative controls, e.g. signage or instruction, not chosen
No level has been chosen yet.
Planning and preparation
Planning/preparation
Liaise with Principal Contractor to identify on-site safety systems and procedures
Establish supervisory and communication arrangements
Principal contractor to confirm emergency response procedures are in place.
Hold points
Hold points identified and signed off before continuing work. Specify?
Training/licence
All workers to have a General Construction Induction Card
Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.
Trained First Aider on site
All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.
Worker duties and responsibilities
Fit condition for work, i.e., no signs of fatigue, alcohol or drugs
Attend all site inductions/briefings
Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)
Only carry out work related to the contract
Inspect completed work and report possible safety, environmental and quality matters to the supervisor.
Monitor/review
All people involved in the task must have this SWMS communicated to them before work commences
SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident
If additional site hazards identified, review this SWMS and amend control measures to suit
People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP
Give the principal contractor a copy of the revised SWMS
The site supervisor to monitor works against the controls stated in this SWMS
SWMS must be kept on-site and made available for inspection or review
Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident
Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.
Site-specific notes
Legislation and codes of practice
Western Australia
Standards
- AS 3610-1995 Formwork for concrete
Personal protective equipment
- Foot Protection
- Hearing Protection
- High Visibility
- Head Protection
- Eye Protection
- Hand Protection
- Sun Protection
Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.
Job steps, hazards and controls
- Work activity
Formwork design
- Hazard
Personal injury, property damage &/or environmental incident
Before controls3 HighControlsProject documentation. Ensure:
Formwork documentation and drawings are available
Experienced formwork designers/engineers used for the design of formwork
Safety aspects of construction & dismantling of the formwork considered in the design
The formwork should be able to be removed easily and safely without excessive force or the need to work in awkward positions
Formwork drawings should include all details of the size and spacing of framing details and, any proprietary fittings or systems to be used.
Vertical pour rates for walls; columns & other vertical concrete elements must be included in the project documentation to prevent blow out/movement of forms during the pouring
Guardrail systems including toe boards, scaffolding or other controls for working at height must be included
Check that the formwork system, both traditional and modular, satisfy AS3610 - Formwork for concrete & AS3600 - Concrete structures.
Do not commence work unless the approved plans for the formwork structure is in place.
After controls2 ModerateResponsible- Supervisorto check
IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute
Overall risk after controls2 MModeratethe highest rating after controls
20 more job steps, from Arrival on-site & assess onsite conditions to Emergency response
Each with its hazards, risk ratings and controls, plus your crew's sign-on.