Site management plan
Is the work associated with a Construction Project? Yes / No
If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.
High-risk construction work
This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)
- Gas Mains
- Hazardous Lines
- Energised Electrical
- Water & Drowning
Planning and preparation
Planning/Preparation
Liaise with Principal Contractor to identify on-site safety systems and procedures
Establish supervisory and communication arrangements
Principal contractor to confirm emergency response procedures are in place.
Hold points
Hold points identified and signed off before continuing work. (specify the hold points)
(specify the hold points)
Training and licence
All workers to have a General Construction Induction Card
Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.
Trained First Aider on site
All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.
Worker duties and responsibilities
Fit condition for work, i.e., no signs of fatigue, alcohol or drugs
Attend all site inductions/briefings
Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)
Only carry out work related to the contract
Inspect completed work and report possible safety, environmental and quality matters to the supervisor.
Monitoring and review
All people involved in the task must have this SWMS communicated to them before work commences
SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident
If additional site hazards identified, review this SWMS and amend control measures to suit
People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP
Give the principal contractor a copy of the revised SWMS
The site supervisor to monitor works against the controls stated in this SWMS
SWMS must be kept on-site and made available for inspection or review
Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident
Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.
Site-specific notes
Legislation and codes of practice
None listed.
Personal protective equipment (PPE)
- Foot Protection
- Eye Protection
- Protective Clothing
- Life Jacket
- Goggles Snorkel
Job steps, hazards and controls
- Work activity
Working alone
- Hazard
Emergency
Before controls3 HighControlsA ‘Buddy’ system must be utilised at all times when working alone. Ensure:
Mobile phone (with service in the work area, pre-programmed with emergency numbers)
Mobile tested before departure & phones have spare, fully charged batteries and facilities for continuing charging
Mobile phones to be kept on the relevant worker at all times
Mobile phones to be kept switched on
Worker calls supervisor upon arrival and departure and regular call-ins are made
Supervisor must have address details, expected arrival/departure and visit duration times
Supervisors have details of relevant worker’s vehicle (registration, colour make, model)
Workers to attend only the site directed by supervisor
Emergency procedures in place if call-ins are not followed, or communication lost with relevant worker
Call-in times must be agreed with the worker and supervisor and based on the risk level expected at the site.
After controls2 ModerateResponsible- Supervisor
IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute
Overall risk after controls2 MModeratethe highest rating after controls
11 more job steps, from Transporting chemicals to Emergency response