Steel Liner Installation

SWMS · SWMS-10603

  • 15 job steps
  • Version 3
  • Miscellaneous
  • Reads on any phone

This Steel Liner Installation SWMS outlines the hazards and controls associated with the installation of steel liners, focusing on high-risk construction work activities including mobile plant movement and the risk of falls from height.

It takes your crew through 15 job steps, from planning and arriving on site to delivery of the plant, work area set-up, drilling the bored pier, placing the steel liner with a crane, steel and concrete placement, plant maintenance, completion and emergency response.

It suits businesses and contractors involved in construction, particularly those specialising in steel liner installation, and the safety officers and site managers responsible for maintaining WHS standards on construction sites.

Preview of the Steel Liner Installation SWMS

Steel Liner Installation

SWMSVersion 3
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
[Principal contractor]
PC Address
—
PC phone
[PC phone]
Date SWMS provided to PC
—
Job Site Address
[Site address]
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile PlantMobile plant movement
  • FallsInvolves a risk of a person falling from 2m or more, including work on telecommunications towers

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. Specify?

Training and licences

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Head Protection
  • Eye Protection
  • Hand Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Planning

    • Hazard

      Contact with utilities/services

      Before controls4 Acute
      Controls
      • Identify the presence of all underground, aboveground or overhead utilities or services at the proposed excavation site:

        • Dial Before You Dig (Telephone Service 1100) as a minimum

        • Site surveys, drawings and plans

      • If identified, ensure the location, clearance distances, alignments and other relevant information is shown on utility drawings for the work.

      • All details must be clearly marked on these documents.

      After controls2 Moderate
      Responsible
      • Supervisor
    • Hazard

      Exposure to silica dust

      Before controls4 Acute
      Controls
      • Training and information provided to workers on RCS should include:

        • Identification of RCS dust through Material/Safety Datasheet (M/SDS) or labels

        • Dust exposure prevention

        • Checking controls are working and using them

        • When and how to use any respiratory protective equipment provided and what to do if something goes wrong (Including worker respirator fit and check processes)

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

14 more job steps, from Arrival on-site & assess onsite conditions to Emergency response

Each with its hazards, risk ratings and controls, plus your crew's sign-on.

Preview as

How it reads in a browser

Get this template

Sign up free, then choose how you'd like it. Your company details fill in for you.

  • Included in paid plans

    Use template credits from your plan. This one costs 1.

    Compare plans and prices
  • Buy it once

    $89.95 paid once, and it's yours to keep. Works on the free plan too.

No card needed to sign up. Early access members get 30% off any plan.

What it covers

15 job steps

  1. PlanningIdentify underground services and prepare for safe excavation
  2. Arrival on-site & assess onsite conditionsSet up safely and assess the site conditions
  3. Check weather conditions & prepareCheck the weather and adjust the work to suit
  4. Delivery and Removal of the PlantLoad, transport and unload the plant safely
  5. Work area set-upSet up the work area to keep the public and workers safe
  6. EnvironmentProtect the environment during the work
  7. House keepingKeep the work area clean and tidy
  8. Manual tasksReduce the risk of manual handling injuries
  9. Connecting attachments/augersAttach the auger and other attachments safely
  10. Bored pier - Screw & unscrewing the liner - Drilling out spoil from inside linerDrill the bored pier and handle the liner safely
  11. Placement & removal of the steel liner using a cranePlace and remove the steel liner using licensed crane crews
  12. Steel & concrete placementPlace the steel and concrete using licensed contractors
  13. Plant maintenance on siteMaintain the plant safely
  14. On completionSecure the site and plant on completion
  15. Emergency responseRespond to emergencies

Hazards it covers

Reviews

No reviews yet.

See all

How templates work

Try it before you pay.

  1. Preview free

    Every template's job steps, hazards and first task are open to read. No sign-up.

  2. Try the editor

    Tailor a demo SWMS with your company, job and site, on a computer or your phone.

  3. Sign up free

    Your details and logo carry over. This template opens already filled in.

  4. Use a credit or buy once

    Paid plans include template credits every month. Or buy this one to keep.