Concrete Boom or Line Pumping

SWMS · SWMS-10065

  • 15 job steps
  • Version 10

This Concrete Boom or Line Pumping Safe Work Method Statement (SWMS) addresses the hazards and controls associated with operating truck-mounted concrete boom and line pumps for safe and efficient operations in various environments.

It covers 15 job steps, from planning, road operation and checking the weather to pump, line and boom set-up, the concrete pour, clearing line blockages, cleaning out pump lines with compressed air, completion and emergency response.

It includes controls for handling hazardous substances, working near powered mobile plant, and operating in various environmental conditions.

It suits concrete pumping companies, construction firms, public works departments and site supervisors.

See its own page

Preview of the Concrete Boom or Line Pumping SWMS

Concrete Boom or Line Pumping

SWMSVersion 10
Company doing the work
[Company]
Business contact
—
Phone #
—
Responsible person (for monitoring SWMS and work)
—
Signature
—
Date
—
Contact phone #
—
Principal contractor (PC)
[Principal contractor]
PC address
—
PC phone #
[PC phone]
Date SWMS provided to PC
—
Job site address
[Site address]
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile PlantMobile plant movement
  • Gas MainsWork on or near pressurised gas distribution mains or piping
  • Hazardous LinesWork on or near chemical, fuel or refrigerant lines
  • Energised ElectricalWork on or near energised electrical installations or services
  • Traffic CorridorsWork carried out adjacent to a road, railway or shipping lane, traffic corridor
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitor/Review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Head Protection
  • Eye Protection
  • Hand Protection
  • Sun Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Planning

    • Hazard

      Unlicensed operator

      Before controls4 Acute
      Controls
      • Ensure operator licensed for the type of vehicle operation. Example:

        • MR (Medium Rigid) = 2 axle, 8T GVM + trailer 9 GVM or less

        • HR (Heavy Rigid) = No axle limit, greater than 8t GVM, + trailer greater than 9 GVM, prime mover or semi-trailer.

      After controls2 Moderate
      Responsible
      • Supervisor
    • Hazard

      Exposure to silica dust

      Before controls4 Acute
      Controls
      • Training and Information provided to workers on respirable crystalline silica (RCS) should include:

        • Identification of RCS dust through Safety Datasheet (SDS) or labels

        • Dust exposure prevention strategies

        • Checking controls are working and using them

        • When and how to use any respiratory protective equipment provided and what to do if something goes wrong (Including worker respirator fit and check processes).

      After controls2 Moderate
      Responsible
      • Supervisor

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

14 more job steps, from Road operation to Emergency response

Each with its hazards, risk ratings and controls, plus your crew's sign-on.

Preview as

How it reads in a browser

Get this system

Sign up free, then choose how you'd like it. Every document goes into your Library, in a folder named for the pack.

  • Included in paid plans

    Use template credits from your plan. This one costs 20.

    Compare plans and prices
  • Buy it once

    $999.90 paid once, and it's yours to keep. Works on the free plan too.

No card needed to sign up. Early access members get 30% off any plan.

What it covers

15 job steps

  1. PlanningConfirm the operator's licence and train workers on silica dust
  2. Road operationInspect the pump truck and drive it safely on the road
  3. Check weather conditions & prepareCheck the weather and prepare for hot or cold conditions
  4. Arrival on-site & assess onsite conditionsPosition the vehicle, report in and assess the site
  5. Pump / Line / Boom setupSet up the pump, line and boom with barriers, exclusion zones, chocks and outriggers
  6. EnvironmentControl noise, air quality, waste, fuels and run-off
  7. House keepingKeep the work area clean and clear of trip hazards
  8. Manual tasksLift and move items safely to avoid strain injuries
  9. Working near powered mobile plantStay alert, visible and clear of operating plant
  10. Hazardous substance / chemical use, e.g. cement powder, hydrochloric acid, and diesel fuel.Handle chemicals as their SDS directs
  11. Concrete pourPour concrete while protecting eyes and skin and controlling hose whip
  12. Clearing line blockagesRelease the pressure and clear line blockages step by step
  13. Cleaning out pump lines with compressed airIsolate the hopper and follow the compressed-air line cleaning procedure
  14. On completionSecure equipment, sign out and leave by the designated routes
  15. Emergency responseCall 000, follow site emergency procedures and report the incident

Hazards it covers

How templates work

Try it before you pay.

  1. Preview free

    Every template's job steps, hazards and first task are open to read. No sign-up.

  2. Try the editor

    Tailor a demo SWMS with your company, job and site, on a computer or your phone.

  3. Sign up free

    Your details and logo carry over. This template opens already filled in.

  4. Use a credit or buy once

    Paid plans include template credits every month. Or buy this one to keep.