Remote Control Trench Roller

SWMS · SWMS-10532

  • 15 job steps
  • Version 3

This Remote Control Trench Roller Safe Work Method Statement (SWMS) covers the hazards and controls for operating a remote control trench roller, including the high-risk construction work involved.

It covers 15 job steps: checking the weather, working alone, arriving on-site, transporting, loading and unloading the roller, work area set-up, environment, housekeeping, manual tasks, communicating with ground workers, trench roller operation, working in trenches deeper than 1.5 m, working near powered mobile plant, hydraulic equipment, completion and emergency response.

It suits businesses and workers in construction and civil engineering who operate or work near remote control trench rollers, and the safety officers and site supervisors responsible for them.

See its own page

Preview of the Remote Control Trench Roller SWMS

Remote Control Trench Roller

SWMSVersion 3

Document details

Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
—
PC Address
—
PC phone
—
Date SWMS provided to PC
—
Job Site Address
—
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile PlantMobile plant movement
  • Shafts & TrenchesWorking at depths greater than 1.5 metres, including tunnels or mines
  • Hazardous AtmosphereWork in an area that may have a contaminated or flammable atmosphere
  • Traffic CorridorsWork carried out adjacent to a road, railway or shipping lane, traffic corridor

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold Points

  • Hold points identified and signed off before continuing work. (specify the hold points)

Training/Licence

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment

  • Foot Protection
  • Hearing Protection
  • High Visibility
  • Head Protection
  • Eye Protection
  • Hand Protection
  • Protective Clothing
  • Breathing Protection
  • Sun Protection

Job steps, hazards and controls

  • Work activity

    Check weather conditions & prepare

    • Hazard

      Extreme weather

      Before controls3 High
      Controls
      • Check weather conditions – do not work in extreme conditions

      • Reschedule works to work in more moderate temperatures.

      After controls2 Moderate
      Responsible
      • Supervisorto maintain awareness of weather conditions
      • Operatorto follow controls
    • Hazard

      Hyperthermia Hypothermia

      Before controls3 High
      Controls
      • Ensure vehicle cabin is air-conditioned

      • Workers trained to recognise the symptoms of hyperthermia and hypothermia

      • Hot conditions. Ensure:

        • Suitable protective clothing

        • Sun brim on hard hats

        • Safety glasses - UV rated

        • Use 30+ sunscreen on exposed skin

        • Adequate drinking water

        • Access to shade on breaks

        • Adequate breaks.

      • Cold conditions. Ensure:

        • Schedule warm-up breaks

        • Hold breaks inside

        • Dress warmly in layers

        • Stay dry (wet clothing chills the body rapidly)

        • Workers must get out of the cold as soon as they can if starting to feel symptoms

        • Alcohol, cigarettes, caffeine and certain medications increase susceptibility to cold.

      After controls2 Moderate
      Responsible
      • Supervisorto maintain awareness of weather conditions
      • Operatorto follow controls

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

14 more job steps, from Working alone to Emergency response

Each with its hazards, risk ratings and controls, plus your crew's sign-on.

Preview as

How it reads in a browser

Get this value pack

Sign up free, then choose how you'd like it. Every document goes into your Library, in a folder named for the pack.

  • Included in paid plans

    Use template credits from your plan. This pack costs 22 instead of 35.

    Compare plans and prices
  • Buy it once

    $1,978.90 $3,148.25 paid once, and it's yours to keep. Works on the free plan too.

No card needed to sign up. Early access members get 30% off any plan.

What it covers

15 job steps

  1. Check weather conditions & prepareCheck the weather and protect workers from heat and cold
  2. Working aloneKeep in contact when working alone
  3. Arrival on-site & assess onsite conditionsAssess the site conditions on arrival
  4. Transporting/ loading/ unloading the trench rollerTransport, load and unload the trench roller safely
  5. Work area set-upSet up the work area near traffic and the public
  6. EnvironmentManage waste, noise, vibration and other environmental impacts
  7. House keepingKeep the work area clean and tidy
  8. Manual tasksReduce the risk of manual task injuries
  9. Establish a communication system with ground workersSet up communication with ground workers
  10. Trench roller operationOperate the trench roller and respond to machine failure
  11. Operation in trenches >1.5m depthControl the risks of working in trenches deeper than 1.5 m
  12. Working near any powered mobile plantWork safely near powered mobile plant
  13. Hydraulic equipmentAttach and use hydraulic equipment safely
  14. On completionShut down the trench roller and leave the site safely
  15. Emergency responseRespond to emergencies

Hazards it covers

How templates work

Try it before you pay.

  1. Preview free

    Every template's job steps, hazards and first task are open to read. No sign-up.

  2. Try the editor

    Tailor a demo SWMS with your company, job and site, on a computer or your phone.

  3. Sign up free

    Your details and logo carry over. This template opens already filled in.

  4. Use a credit or buy once

    Paid plans include template credits every month. Or buy this one to keep.