Shed Construction

SWMS · SWMS-10480

  • 14 job steps
  • Version 5
  • Steel Construction
  • Reads on any phone

This Shed Construction Safe Work Method Statement (SWMS) guides the safe delivery and assembly of steel sheds. It addresses the hazards and the controls needed for high-risk construction work such as mobile plant movement and the risk of falls from height.

It covers 14 job steps, from planning, weather checks, arrival on site, materials delivery and work area set-up to working at height, tool use, hazardous chemicals, shed erection, completion and emergency response.

It includes controls for the environment, housekeeping and manual tasks, silica dust, and craning roof trusses.

It suits businesses and contractors who build steel sheds, and the site supervisors and safety officers who enforce compliance.

Preview of the Shed Construction SWMS

Shed Construction

SWMSVersion 5
Company doing the work
[Company]
Business contact and phone
—
Responsible person (for monitoring SWMS and work)
—
Responsible person's phone
—
Responsible person's signature
—
Date signed
—
Principal Contractor (PC)
[Principal contractor]
PC Address
—
PC phone
[PC phone]
Date SWMS provided to PC
—
Job Site Address
[Site address]
Part of a construction project
—

Site management plan

If the work is part of a construction project, this SWMS must align with requirements of the Site Management Plan in place for the Construction Project.

High-risk construction work

This work activity involves the following “High-Risk Construction Work” (HRCW - identified in the Job Task column)

  • Mobile PlantMobile plant movement
  • FallsInvolves a risk of a person falling from 2m or more, including work on telecommunications towers

Working with a risk of a fall over 2 metres

The fall from height hierarchy of control level considered when establishing controls:

  • L1Work on the ground or solid construction, not chosen
  • L2Use a passive fall restraint system, e.g. guard rails, scaffolding, EWP, not chosen
  • L3Use a work positioning system, e.g. travel restraint, rope access, not chosen
  • L4Use a fall arrest system, e.g. safety harness, catch platforms, not chosen
  • L5Implement administrative controls, e.g. signage or instruction, not chosen

No level has been chosen yet.

Planning and preparation

Planning/Preparation

  • Liaise with Principal Contractor to identify on-site safety systems and procedures

  • Establish supervisory and communication arrangements

  • Principal contractor to confirm emergency response procedures are in place.

Hold points

Hold points identified and signed off before continuing work. (specify the hold points)

Training and licences

  • All workers to have a General Construction Induction Card

  • Relevant workers have relevant certificates of competency, licenses, and training. Specify on the SWMS Sign-off for each worker.

  • Trained First Aider on site

  • All workers trained in site-specific emergency and evacuation procedures, SWMS, safe work procedures, and safety data sheets.

Worker duties and responsibilities

  • Fit condition for work, i.e., no signs of fatigue, alcohol or drugs

  • Attend all site inductions/briefings

  • Comply with all site requirements, e.g. PPE, Traffic Management Plans (TMP)

  • Only carry out work related to the contract

  • Inspect completed work and report possible safety, environmental and quality matters to the supervisor.

Monitoring and review

  • All people involved in the task must have this SWMS communicated to them before work commences

  • SWMS to be reviewed and amended if necessary, in consultation with relevant people after any near miss or incident

  • If additional site hazards identified, review this SWMS and amend control measures to suit

  • People, including workers, contractors and sub-contractors, affected by the revisions to this SWMS, must be informed ASAP

  • Give the principal contractor a copy of the revised SWMS

  • The site supervisor to monitor works against the controls stated in this SWMS

  • SWMS must be kept on-site and made available for inspection or review

  • Keep a record of this SWMS until the job is complete or for two years if involved in a notifiable incident

  • Regardless of any other factor, the person in control of the workplace must review this SWMS at least annually.

Site-specific notes

Legislation and codes of practice

None listed.

Personal protective equipment (PPE)

  • Foot Protection
  • Head Protection
  • Eye Protection
  • Sun Protection

Do not wear rings, watches or jewellery that may become entangled. Long and loose hair must be tied back.

Job steps, hazards and controls

  • Work activity

    Planning & preparation

    • Hazard

      Falls from heights > 2m.

      Before controls4 Acute
      Controls
      • Conduct a risk assessment for working at height

      • Based on the Risk Assessment, ensure the highest possible level of controls is adopted.

      • More than one measure can be used to reduce risk. For example, engineering controls like edge protection can be implemented with administrative controls such as training and use of this SWMS, while wearing PPE (non-slip shoes).

      • Ensure a dedicated SWMS is in place for height access, e.g., EWP, rope access, mesh or other systems.

      After controls2 Moderate
      Responsible
      • Supervisors

IR before controls · RR after controls1 LLow2 MModerate3 HHigh4 AAcute

Overall risk after controls2 MModeratethe highest rating after controls

13 more job steps, from Check weather conditions & prepare to Emergency response

Each with its hazards, risk ratings and controls, plus your crew's sign-on.

Preview as

How it reads in a browser

Get this template

Sign up free, then choose how you'd like it. Your company details fill in for you.

  • Included in paid plans

    Use template credits from your plan. This one costs 1.

    Compare plans and prices
  • Buy it once

    $89.95 paid once, and it's yours to keep. Works on the free plan too.

No card needed to sign up. Early access members get 30% off any plan.

What it covers

14 job steps

  1. Planning & preparationAssess the risk of working at height and choose the controls
  2. Check weather conditions & prepareCheck the weather and manage hot and cold conditions
  3. Arrival on-site & assess onsite conditionsReport to site, assess conditions and induct workers
  4. Materials deliveryReceive and unload deliveries safely
  5. Work area set-upBarricade the work area and control access
  6. Working at height on ladders, trestles, mobile scaffold, fixed scaffold & openingsWork at height on ladders, scaffolds and around openings
  7. EnvironmentControl noise, dust, waste, spills and animals on site
  8. House keepingKeep the work area clean and clear of trip hazards
  9. Manual tasksMove and store materials to reduce manual handling injury
  10. Working with powered & non-powered toolsUse powered and non-powered tools safely
  11. Hazardous substance /chemical useUse hazardous chemicals as the SDS directs
  12. Shed constructionErect and brace the frame, fix sheeting and crane trusses
  13. On completionDismantle the scaffold, clean up and sign out of site
  14. Emergency responseRespond to emergencies

Hazards it covers

Reviews

No reviews yet.

See all

How templates work

Try it before you pay.

  1. Preview free

    Every template's job steps, hazards and first task are open to read. No sign-up.

  2. Try the editor

    Tailor a demo SWMS with your company, job and site, on a computer or your phone.

  3. Sign up free

    Your details and logo carry over. This template opens already filled in.

  4. Use a credit or buy once

    Paid plans include template credits every month. Or buy this one to keep.